Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
8,551
matching recommendationsSIC | 36 | Electronic & Other Electric Equipment |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
DL0220 # 07 Y:2023 | 07 | 2023 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $3,578 | $0 | Not Implemented |
DL0220 # 08 Y:2023 | 08 | 2023 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $4,694 | $0 | Not Implemented |
DL0220 # 09 Y:2023 | 09 | 2023 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $6,332 | $20,000 | Not Implemented |
DL0220 # 10 Y:2023 | 10 | 2023 | RECOVER WASTE HEAT FROM EQUIPMENT | $6,153 | $9,740 | Not Implemented |
DL0220 # 11 Y:2023 | 11 | 2023 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,387 | $6,500 | Not Implemented |
DL0220 # 12 Y:2023 | 12 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,150 | $8,994 | Implemented |
WV0637 # 01 Y:2023 | 01 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $7,145 | $8,026 | Not Implemented |
WV0637 # 02 Y:2023 | 02 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,462 | $188 | Implemented |
WV0637 # 03 Y:2023 | 03 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,065 | $3,353 | Implemented |
WV0637 # 04 Y:2023 | 04 | 2023 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $678 | $50 | Implemented |
WV0637 # 05 Y:2023 | 05 | 2023 | UPGRADE CONTROLS ON COMPRESSORS | $572 | $1,465 | Not Implemented |
WV0637 # 06 Y:2023 | 06 | 2023 | DEVELOP A REPAIR/REPLACE POLICY | $502 | $617 | Implemented |
WV0637 # 07 Y:2023 | 07 | 2023 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $164 | $483 | Implemented |
WV0637 # 08 Y:2023 | 08 | 2023 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $122 | $600 | Implemented |
CM1013 # 01 Y:2022 | 01 | 2022 | USE SOLAR HEAT TO MAKE ELECTRICTY | $10,211 | $116,226 | n/a |
CM1013 # 02 Y:2022 | 02 | 2022 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $8,342 | $3,480 | n/a |
CM1013 # 03 Y:2022 | 03 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,819 | $3,590 | n/a |
CM1013 # 04 Y:2022 | 04 | 2022 | INSTALL OCCUPANCY SENSORS | $465 | $260 | n/a |
DL0217 # 01 Y:2023 | 01 | 2023 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $14,180 | $0 | Implemented |
DL0217 # 02 Y:2023 | 02 | 2023 | TURN OFF EQUIPMENT WHEN NOT IN USE | $2,621 | $0 | Implemented |
DL0217 # 03 Y:2023 | 03 | 2023 | INSTALL DESICCANT HUMIDITY CONTROL SYSTEM | $112,250 | $0 | Not Implemented |
DL0217 # 04 Y:2023 | 04 | 2023 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $7,120 | $0 | Implemented |
DL0217 # 05 Y:2023 | 05 | 2023 | REDUCE VENTILATION AIR | $29,580 | $0 | Implemented |
DL0217 # 06 Y:2023 | 06 | 2023 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $30,600 | $0 | Implemented |
DL0217 # 07 Y:2023 | 07 | 2023 | REDUCE VENTILATION AIR | $2,650 | $0 | Implemented |