Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
753
matching recommendationsSIC | 36 | Electronic & Other Electric Equipment |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SD0112 # 03 Y:1995 | 03 | 1995 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $1,144 | $1,600 | Implemented |
SD0112 # 04 Y:1995 | 04 | 1995 | INSULATE BARE EQUIPMENT | $2,282 | $563 | Implemented |
SD0112 # 05 Y:1995 | 05 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,168 | $6,733 | Implemented |
SD0112 # 06 Y:1995 | 06 | 1995 | INSTALL SPECTRAL REFLECTORS / DELAMP | $5,047 | $4,305 | Implemented |
SD0112 # 07 Y:1995 | 07 | 1995 | INSTALL OCCUPANCY SENSORS | $494 | $599 | Not Implemented |
SD0112 # 08 Y:1995 | 08 | 1995 | INSTALL TIMERS AND/OR THERMOSTATS | $1,306 | $849 | Implemented |
SD0112 # 09 Y:1995 | 09 | 1995 | REDUCE SOLUTION DRAG-OUT TO PREVENT SOLUTION LOSS | $730 | $250 | Implemented |
SD0112 # 10 Y:1995 | 10 | 1995 | USE IN-PROCESS RECYCLING WHENEVER POSSIBLE | $2,184 | $0 | Not Implemented |
SD0112 # 11 Y:1995 | 11 | 1995 | USE HIGH QUALITY SCRAP (LOW SULFUR) TO REDUCE HAZARDOUS SLUDGE GENERATION | $1,069 | $1,000 | Implemented |
SD0110 # 01 Y:1995 | 01 | 1995 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $6,147 | $0 | Not Implemented |
SD0110 # 02 Y:1995 | 02 | 1995 | RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR | $2,764 | $2,310 | Not Implemented |
SD0110 # 03 Y:1995 | 03 | 1995 | RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR | $878 | $860 | Not Implemented |
SD0110 # 04 Y:1995 | 04 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $12,654 | $30,715 | Not Implemented |
SD0110 # 05 Y:1995 | 05 | 1995 | INSTALL SPECTRAL REFLECTORS / DELAMP | $21,143 | $16,440 | Not Implemented |
SD0110 # 06 Y:1995 | 06 | 1995 | INSTALL OCCUPANCY SENSORS | $3,279 | $1,584 | Not Implemented |
SF0047 # 01 Y:1995 | 01 | 1995 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,510 | $516 | Implemented |
SF0047 # 02 Y:1995 | 02 | 1995 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $12,565 | $4,400 | Not Implemented |
SF0047 # 03 Y:1995 | 03 | 1995 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,063 | $1,400 | Implemented |
SF0047 # 04 Y:1995 | 04 | 1995 | INSTALL / REPAIR INSULATION ON STEAM LINES | $1,794 | $605 | Not Implemented |
SF0047 # 05 Y:1995 | 05 | 1995 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,711 | $4,400 | Not Implemented |
SF0047 # 06 Y:1995 | 06 | 1995 | USE EXISTING DAM TO GENERATE ELECTRICITY | $59,850 | $122,000 | Not Implemented |
SF0047 # 07 Y:1995 | 07 | 1995 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $46,406 | $42,000 | Not Implemented |
SD0104 # 01 Y:1995 | 01 | 1995 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $24,474 | $22,100 | Implemented |
SD0104 # 02 Y:1995 | 02 | 1995 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $4,382 | $9,800 | Not Implemented |
SD0104 # 03 Y:1995 | 03 | 1995 | RECOVER HEAT FROM EXHAUSTED STEAM, HOT AIR OR HOT WATER | $3,356 | $3,400 | Not Implemented |