Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
249
matching recommendationsSIC | 36 | Electronic & Other Electric Equipment |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
GT0526 # 07 Y:1994 | 07 | 1994 | INSTALL HEAT PIPES / RAISE COOLING SETPOINT | $189,570 | $279,700 | Not Implemented |
GT0524 # 01 Y:1994 | 01 | 1994 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,680 | $1,300 | Not Implemented |
GT0524 # 02 Y:1994 | 02 | 1994 | RECOVER WASTE HEAT FROM EQUIPMENT | $3,160 | $5,030 | Not Implemented |
GT0524 # 03 Y:1994 | 03 | 1994 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $9,250 | $8,000 | Not Implemented |
GT0524 # 04 Y:1994 | 04 | 1994 | USE COOLING TOWER WATER INSTEAD OF REFRIGERATION | $2,930 | $5,800 | Not Implemented |
GT0524 # 05 Y:1994 | 05 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,355 | $7,813 | Not Implemented |
GT0524 # 06 Y:1994 | 06 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,707 | $51,104 | Not Implemented |
GT0524 # 07 Y:1994 | 07 | 1994 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $4,370 | $11,000 | Not Implemented |
GT0511 # 01 Y:1993 | 01 | 1993 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,040 | $650 | Implemented |
GT0511 # 02 Y:1993 | 02 | 1993 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,540 | $2,900 | Implemented |
GT0511 # 03 Y:1993 | 03 | 1993 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $33,500 | $37,440 | Implemented |
GT0511 # 04 Y:1993 | 04 | 1993 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $980 | $1,440 | Not Implemented |
GT0511 # 05 Y:1993 | 05 | 1993 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $5,720 | $0 | Not Implemented |
GT0511 # 06 Y:1993 | 06 | 1993 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $27,055 | $45,000 | Not Implemented |
GT0500 # 01 Y:1993 | 01 | 1993 | INSTALL OCCUPANCY SENSORS | $170 | $480 | Implemented |
GT0500 # 02 Y:1993 | 02 | 1993 | ISOLATE HOT OR COLD EQUIPMENT | $1,860 | $4,000 | Implemented |
GT0500 # 03 Y:1993 | 03 | 1993 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $1,610 | $500 | Implemented |
GT0500 # 04 Y:1993 | 04 | 1993 | AIR CONDITION ONLY SPACE NECESSARY | $24,500 | $31,800 | Not Implemented |
GT0500 # 05 Y:1993 | 05 | 1993 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $2,230 | $0 | Implemented |
GT0493 # 01 Y:1993 | 01 | 1993 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $15,390 | $49,500 | Not Implemented |
GT0493 # 02 Y:1993 | 02 | 1993 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $6,840 | $13,000 | Not Implemented |
GT0493 # 03 Y:1993 | 03 | 1993 | USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE | $1,260 | $0 | Implemented |
GT0493 # 04 Y:1993 | 04 | 1993 | REDUCE VENTILATION AIR | $1,680 | $7,500 | Implemented |
GT0493 # 05 Y:1993 | 05 | 1993 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $11,650 | $28,350 | Not Implemented |
GT0475 # 01 Y:1992 | 01 | 1992 | RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR | $11,700 | $0 | Implemented |