Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
68
matching recommendationsSIC | 36 | Electronic & Other Electric Equipment |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
DL0217 # 06 Y:2023 | 06 | 2023 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $30,600 | $0 | Implemented |
DL0217 # 01 Y:2023 | 01 | 2023 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $14,180 | $0 | Implemented |
DL0217 # 10 Y:2023 | 10 | 2023 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $1,110 | $5,000 | Not Implemented |
DL0217 # 07 Y:2023 | 07 | 2023 | REDUCE VENTILATION AIR | $2,650 | $0 | Implemented |
DL0217 # 09 Y:2023 | 09 | 2023 | RECOVER WASTE HEAT FROM EQUIPMENT | $5,708 | $15,000 | Not Implemented |
DL0217 # 13 Y:2023 | 13 | 2023 | USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE | $1,390 | $11,744 | Not Implemented |
DL0217 # 12 Y:2023 | 12 | 2023 | USE "HEAT WHEEL" OR OTHER HEAT EXCHANGER TO CROSS-EXCHANGE BUILDING EXHAUST AIR WITH MAKE-UP AIR | $6,950 | $25,000 | Not Implemented |
DL0217 # 11 Y:2023 | 11 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,318 | $4,100 | Implemented |
DL0217 # 05 Y:2023 | 05 | 2023 | REDUCE VENTILATION AIR | $29,580 | $0 | Implemented |
DL0217 # 04 Y:2023 | 04 | 2023 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $7,120 | $0 | Implemented |
DL0217 # 08 Y:2023 | 08 | 2023 | REDUCE VENTILATION AIR | $1,715 | $750 | Implemented |
DL0217 # 03 Y:2023 | 03 | 2023 | INSTALL DESICCANT HUMIDITY CONTROL SYSTEM | $112,250 | $0 | Not Implemented |
DL0217 # 02 Y:2023 | 02 | 2023 | TURN OFF EQUIPMENT WHEN NOT IN USE | $2,621 | $0 | Implemented |
DL0173 # 01 Y:2017 | 01 | 2017 | UPGRADE CONTROLS ON COMPRESSORS | $20,880 | $0 | Implemented |
DL0173 # 02 Y:2017 | 02 | 2017 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,435 | $15,000 | Implemented |
DL0173 # 03 Y:2017 | 03 | 2017 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $5,100 | $9,375 | Not Implemented |
DL0173 # 04 Y:2017 | 04 | 2017 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $1,676 | $1,375 | Implemented |
DL0173 # 05 Y:2017 | 05 | 2017 | RECOVER WASTE HEAT FROM EQUIPMENT | $2,364 | $654 | Not Implemented |
DL0173 # 06 Y:2017 | 06 | 2017 | UPGRADE OBSOLETE EQUIPMENT | $17,600 | $5,950 | Implemented |
DL0173 # 07 Y:2017 | 07 | 2017 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $8,800 | $3,940 | Not Implemented |
DL0171 # 09 Y:2016 | 09 | 2016 | INSTALL AUTOMATIC STACK DAMPER | $624 | $205 | Not Implemented |
DL0171 # 10 Y:2016 | 10 | 2016 | USE SEPARATE SWITCHES ON PERIMETER LIGHTING WHICH MAY BE TURNED OFF WHEN NATURAL LIGHT IS AVAILABLE | $2,505 | $1,524 | Not Implemented |
DL0171 # 07 Y:2016 | 07 | 2016 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $2,885 | $0 | Implemented |
DL0171 # 01 Y:2016 | 01 | 2016 | INSTALL SYSTEM TO COLLECT SCRAP | $4,328 | $360 | Not Implemented |
DL0171 # 02 Y:2016 | 02 | 2016 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $4,059 | $4,224 | Not Implemented |