Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
205
matching recommendationsSIC | 3624 | Carbon And Graphite Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
LE0564 # 04 Y:2024 | 04 | 2024 | INSTALL TIMERS AND/OR THERMOSTATS | $3,800 | $400 | n/a |
LE0564 # 10 Y:2024 | 10 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $697 | $3,400 | n/a |
LE0564 # 01 Y:2024 | 01 | 2024 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $1,016 | $0 | n/a |
LE0564 # 11 Y:2024 | 11 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $12,320 | $61,333 | n/a |
LE0564 # 09 Y:2024 | 09 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,861 | $13,312 | n/a |
LE0564 # 08 Y:2024 | 08 | 2024 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $1,023 | $4,500 | n/a |
LE0564 # 07 Y:2024 | 07 | 2024 | RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR | $1,314 | $4,000 | n/a |
LE0564 # 06 Y:2024 | 06 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $357 | $1,080 | n/a |
LE0564 # 05 Y:2024 | 05 | 2024 | REDUCE INFILTRATION TO REFRIGERATED AREAS; ISOLATE HOT EQUIPMENT FROM REFRIGERATED AREAS | $10,054 | $5,500 | n/a |
LE0564 # 03 Y:2024 | 03 | 2024 | INSTALL TIMERS AND/OR THERMOSTATS | $5,156 | $200 | n/a |
LE0564 # 02 Y:2024 | 02 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,789 | $100 | n/a |
UU0242 # 08 Y:2024 | 08 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $10,658 | $13,800 | Implemented |
UU0242 # 09 Y:2024 | 09 | 2024 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $12,487 | $68,600 | Not Implemented |
UU0242 # 10 Y:2024 | 10 | 2024 | UPGRADE OBSOLETE EQUIPMENT | $12,250 | $84,300 | Implemented |
UU0242 # 05 Y:2024 | 05 | 2024 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $8,004 | $11,422 | Not Implemented |
UU0242 # 04 Y:2024 | 04 | 2024 | INSTALL OCCUPANCY SENSORS | $5,187 | $5,143 | Implemented |
UU0242 # 06 Y:2024 | 06 | 2024 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $21,730 | $82,100 | Not Implemented |
UU0242 # 02 Y:2024 | 02 | 2024 | CLOSE OFF UNNEEDED STEAM LINES | $10,220 | $4,400 | Not Implemented |
UU0242 # 03 Y:2024 | 03 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $14,164 | $37,300 | Implemented |
UU0242 # 07 Y:2024 | 07 | 2024 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $6,520 | $9,510 | Implemented |
UU0242 # 01 Y:2024 | 01 | 2024 | TURN OFF EQUIPMENT WHEN NOT IN USE | $139,774 | $4,000 | Implemented |
NT0019 # 02 Y:2024 | 02 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $17,486 | $33,471 | Not Implemented |
NT0019 # 04 Y:2024 | 04 | 2024 | APPLY FOR INVESTMENT INCENTIVES | $12,574 | $0 | Not Implemented |
NT0019 # 01 Y:2024 | 01 | 2024 | INSULATE BARE EQUIPMENT | $60,556 | $294,320 | Not Implemented |
NT0019 # 03 Y:2024 | 03 | 2024 | OPTIMIZE PLANT POWER FACTOR | $36,036 | $9,814 | Not Implemented |