matching recommendationsSIC | 3629 | Electrical Industrial Apparatus, Nec |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MA0693 # 01 Y:2012 | 01 | 2012 | PAY UTILITY BILLS ON TIME | $25,247 | $500 | Implemented |
MA0693 # 02 Y:2012 | 02 | 2012 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $15,776 | $43,000 | Not Implemented |
MA0693 # 03 Y:2012 | 03 | 2012 | REPAIR AND ELIMINATE STEAM LEAKS | $9,000 | $4,200 | Implemented |
MA0693 # 04 Y:2012 | 04 | 2012 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $6,573 | $27,000 | Not Implemented |
MA0693 # 05 Y:2012 | 05 | 2012 | INSTALL OCCUPANCY SENSORS | $1,572 | $4,200 | Implemented |
MA0693 # 06 Y:2012 | 06 | 2012 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $486 | $200 | Not Implemented |
MA0693 # 07 Y:2012 | 07 | 2012 | INSULATE BARE EQUIPMENT | $373 | $600 | Not Implemented |
OK0826 # 01 Y:2012 | 01 | 2012 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $17,497 | $27,016 | Not Implemented |
OK0826 # 02 Y:2012 | 02 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $50,910 | $106,879 | Not Implemented |
OK0826 # 03 Y:2012 | 03 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $25,061 | $38,900 | Not Implemented |
OK0826 # 04 Y:2012 | 04 | 2012 | COVER OPEN TANKS | $1,576 | $0 | Not Implemented |
OK0826 # 05 Y:2012 | 05 | 2012 | REDUCE EXCESSIVE BOILER BLOWDOWN | $13,280 | $31,040 | Not Implemented |
OK0826 # 06 Y:2012 | 06 | 2012 | INSTALL / REPAIR INSULATION ON STEAM LINES | $4,630 | $4,000 | Not Implemented |
OK0826 # 07 Y:2012 | 07 | 2012 | INSTALL / REPAIR INSULATION ON STEAM LINES | $20,532 | $9,400 | Not Implemented |