Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
28
matching recommendationsSIC | 364 | Electric Lighting And Wiring Equipment |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WI0515 # 05 Y:2006 | 05 | 2006 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,038 | $1,280 | Implemented |
WI0515 # 04 Y:2006 | 04 | 2006 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,559 | $0 | Implemented |
WI0515 # 03 Y:2006 | 03 | 2006 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $2,857 | $3,600 | Not Implemented |
WI0515 # 02 Y:2006 | 02 | 2006 | ELIMINATE SHIFT | $10,200 | $0 | Implemented |
WI0515 # 01 Y:2006 | 01 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $23,672 | $64,000 | Not Implemented |
WI0515 # 06 Y:2006 | 06 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $972 | $0 | Not Implemented |
WI0515 # 07 Y:2006 | 07 | 2006 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $907 | $0 | Not Implemented |
WI0462 # 08 Y:2004 | 08 | 2004 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $369 | $438 | Not Implemented |
WI0462 # 07 Y:2004 | 07 | 2004 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $798 | $840 | Not Implemented |
WI0462 # 06 Y:2004 | 06 | 2004 | UPGRADE CONTROLS ON COMPRESSORS | $808 | $2,500 | Not Implemented |
WI0462 # 05 Y:2004 | 05 | 2004 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $2,319 | $500 | Not Implemented |
WI0462 # 04 Y:2004 | 04 | 2004 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $4,136 | $1,800 | Not Implemented |
WI0462 # 03 Y:2004 | 03 | 2004 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $3,916 | $8,000 | Not Implemented |
WI0462 # 02 Y:2004 | 02 | 2004 | REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT | $8,389 | $14,000 | Not Implemented |
WI0462 # 01 Y:2004 | 01 | 2004 | USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION | $30,420 | $36,000 | Not Implemented |
WI0457 # 01 Y:2003 | 01 | 2003 | USE WASTE HEAT FROM FLUE GASES TO HEAT SPACE CONDITIONING AIR | $7,805 | $11,000 | Not Implemented |
WI0457 # 06 Y:2003 | 06 | 2003 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $331 | $740 | Not Implemented |
WI0457 # 05 Y:2003 | 05 | 2003 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $936 | $200 | Not Implemented |
WI0457 # 04 Y:2003 | 04 | 2003 | REPLACE CLOTH RAGS WITH PAPER TOWELS | $1,413 | $0 | Not Implemented |
WI0457 # 03 Y:2003 | 03 | 2003 | USE REVERSE OSMOSIS TO CONCENTRATE MATERIAL | $3,333 | $8,000 | Not Implemented |
WI0457 # 02 Y:2003 | 02 | 2003 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $3,965 | $800 | Not Implemented |
WI0425 # 01 Y:2002 | 01 | 2002 | INSTALL AUTOMATIC PART STORAGE / RETREVAL SYSTEM | $58,500 | $120,000 | n/a |
WI0425 # 02 Y:2002 | 02 | 2002 | USE FILTRATION, CENTRIFUGING TO REMOVE CONTAMINANTS | $11,400 | $2,000 | n/a |
WI0425 # 03 Y:2002 | 03 | 2002 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $4,750 | $4,800 | n/a |
WI0425 # 04 Y:2002 | 04 | 2002 | COVER OPEN TANKS | $4,508 | $1,512 | n/a |