Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

1,242

matching recommendations
Reset
SIC 364 Electric Lighting And Wiring Equipment
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
BD0208 # 03 Y:2002 03 2002 USE SYNTHETIC LUBRICANT $110 $200 Not Implemented
BD0208 # 04 Y:2002 04 2002 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $100 $400 Implemented
BD0208 # 05 Y:2002 05 2002 MINIMIZE WATER USAGE $105 $400 Not Implemented
TA0026 # 01 Y:2002 01 2002 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $4,400 $1,120 Implemented
TA0026 # 02 Y:2002 02 2002 INSTALL STORM WINDOWS AND DOORS $1,690 $230 Implemented
TA0026 # 03 Y:2002 03 2002 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME $1,230 $0 Not Implemented
TA0026 # 04 Y:2002 04 2002 INSULATE BARE EQUIPMENT $980 $400 Implemented
TA0026 # 05 Y:2002 05 2002 INSTALL OCCUPANCY SENSORS $875 $346 Implemented
TA0026 # 06 Y:2002 06 2002 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $500 $0 Implemented
TA0026 # 07 Y:2002 07 2002 LOWER CEILING TO REDUCE CONDITIONED SPACE $214 $0 Implemented
UD0638 # 01 Y:2002 01 2002 DEVELOP STANDARD OPERATING PROCEDURES $75,000 $10,000 Implemented
UD0638 # 02 Y:2002 02 2002 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $75,000 $17,017 Implemented
UD0638 # 03 Y:2002 03 2002 MAKE A NEW BY-PRODUCT $49,743 $30,000 Implemented
UD0638 # 04 Y:2002 04 2002 SWITCH TO A SOLVENT THAT CAN BE CLEANED AND RE-USED $18,300 $4,175 Not Implemented
UD0638 # 05 Y:2002 05 2002 USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL $9,572 $21,682 Not Implemented
UD0638 # 06 Y:2002 06 2002 INSTALL MOTOR VOLTAGE CONTROLLER ON LIGHTLY LOADED MOTORS $5,079 $18,900 Not Implemented
UD0638 # 07 Y:2002 07 2002 RECOVER WASTE HEAT FROM EQUIPMENT $4,787 $0 Not Implemented
UD0638 # 08 Y:2002 08 2002 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,144 $6,458 Implemented
UD0638 # 09 Y:2002 09 2002 OPTIMIZE PLANT POWER FACTOR $1,935 $1,800 Not Implemented
UD0638 # 10 Y:2002 10 2002 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $1,751 $0 Implemented
UD0638 # 11 Y:2002 11 2002 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $1,211 $250 Implemented
UD0638 # 12 Y:2002 12 2002 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $128 $101 Implemented
TA0021 # 01 Y:2002 01 2002 INSTALL / REPAIR INSULATION ON STEAM LINES $11,450 $5,883 Implemented
TA0021 # 02 Y:2002 02 2002 INCREASE AMOUNT OF CONDENSATE RETURNED $9,736 $19,010 Not Implemented
TA0021 # 03 Y:2002 03 2002 REPAIR AND ELIMINATE STEAM LEAKS $6,110 $190 Implemented