Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
38
matching recommendationsSIC | 367 | Electronic Components And Accessories |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
IP0007 # 04 Y:2013 | 04 | 2013 | RECYCLE AIR FOR HEATING, VENTILATION AND AIR CONDITIONING | $46,311 | $151,951 | Not Implemented |
IP0007 # 03 Y:2013 | 03 | 2013 | OPTIMIZE PLANT POWER FACTOR | $13,528 | $33,600 | Not Implemented |
IP0007 # 02 Y:2013 | 02 | 2013 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,744 | $0 | Implemented |
IP0007 # 01 Y:2013 | 01 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $7,164 | $0 | Implemented |
UD0681 # 14 Y:2003 | 14 | 2003 | INSTALL OCCUPANCY SENSORS | $105 | $160 | Not Implemented |
UD0681 # 01 Y:2003 | 01 | 2003 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $82,000 | $1,490 | Implemented |
UD0681 # 13 Y:2003 | 13 | 2003 | DISCONNECT BALLASTS | $159 | $46 | Implemented |
UD0681 # 12 Y:2003 | 12 | 2003 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $350 | $230 | Not Implemented |
UD0681 # 11 Y:2003 | 11 | 2003 | INSULATE BARE EQUIPMENT | $930 | $1,360 | Implemented |
UD0681 # 09 Y:2003 | 09 | 2003 | REMOVE OR CLOSE OFF UNNEEDED COMPRESSED AIR LINES | $1,095 | $1,268 | Not Implemented |
UD0681 # 02 Y:2003 | 02 | 2003 | MAKE ICE DURING OFF PEAK HOURS FOR COOLING | $26,822 | $100,000 | Not Implemented |
UD0681 # 03 Y:2003 | 03 | 2003 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $13,200 | $8,060 | Not Implemented |
UD0681 # 04 Y:2003 | 04 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,862 | $7,947 | Implemented |
UD0681 # 05 Y:2003 | 05 | 2003 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,840 | $700 | Not Implemented |
UD0681 # 06 Y:2003 | 06 | 2003 | REDUCE VENTILATION AIR | $2,785 | $1,360 | Not Implemented |
UD0681 # 07 Y:2003 | 07 | 2003 | AIR CONDITION ONLY SPACE NECESSARY | $1,800 | $0 | Implemented |
UD0681 # 08 Y:2003 | 08 | 2003 | CENTRALIZE CONTROL OF EXHAUST FANS TO ENSURE THEIR SHUTDOWN, OR ESTABLISH PROGRAM TO ENSURE MANUAL SHUTDOWN | $1,740 | $0 | Implemented |
UD0681 # 10 Y:2003 | 10 | 2003 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,095 | $91 | Not Implemented |
ND0319 # 01 Y:1999 | 01 | 1999 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,025 | $10,705 | Not Implemented |
ND0319 # 02 Y:1999 | 02 | 1999 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $63 | $65 | Implemented |
ND0319 # 03 Y:1999 | 03 | 1999 | INSTALL SKYLIGHTS | $535 | $420 | Not Implemented |
ND0319 # 04 Y:1999 | 04 | 1999 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $411 | $30 | Implemented |
ND0319 # 05 Y:1999 | 05 | 1999 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $380 | $440 | Not Implemented |
ND0319 # 06 Y:1999 | 06 | 1999 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $155 | $40 | Implemented |
ND0319 # 07 Y:1999 | 07 | 1999 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $283 | $510 | Implemented |