Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
68
matching recommendationsSIC | 367 | Electronic Components And Accessories |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WM0012 # 02 Y:2012 | 02 | 2012 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $1,345 | $375 | Not Implemented |
WM0012 # 03 Y:2012 | 03 | 2012 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $771 | $100 | Not Implemented |
WM0012 # 04 Y:2012 | 04 | 2012 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $1,999 | $5,230 | Implemented |
WM0012 # 05 Y:2012 | 05 | 2012 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $2,779 | $4,500 | Not Implemented |
WM0012 # 06 Y:2012 | 06 | 2012 | AIR CONDITION ONLY SPACE NECESSARY | $597 | $975 | Not Implemented |
WM0012 # 07 Y:2012 | 07 | 2012 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $62 | $128 | Implemented |
WM0012 # 01 Y:2012 | 01 | 2012 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,304 | $1,675 | Not Implemented |
AM0623 # 03 Y:2012 | 03 | 2012 | INSTALL DESICCANT HUMIDITY CONTROL SYSTEM | $36,640 | $10,000 | Not Implemented |
AM0623 # 09 Y:2012 | 09 | 2012 | USE SYNTHETIC LUBRICANT | $1,010 | $0 | Not Implemented |
AM0623 # 08 Y:2012 | 08 | 2012 | INSTALL OCCUPANCY SENSORS | $3,100 | $570 | Not Implemented |
AM0623 # 07 Y:2012 | 07 | 2012 | TREAT AND REUSE RINSE WATERS | $3,300 | $3,000 | Not Implemented |
AM0623 # 06 Y:2012 | 06 | 2012 | OPTIMIZE PLANT POWER FACTOR | $4,500 | $8,160 | Not Implemented |
AM0623 # 05 Y:2012 | 05 | 2012 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,538 | $1,045 | Not Implemented |
AM0623 # 04 Y:2012 | 04 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,838 | $500 | Not Implemented |
AM0623 # 02 Y:2012 | 02 | 2012 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $21,800 | $13,240 | Not Implemented |
AM0623 # 01 Y:2012 | 01 | 2012 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $75,600 | $270,000 | Not Implemented |
AM0621 # 04 Y:2012 | 04 | 2012 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $220 | $0 | Not Implemented |
AM0621 # 03 Y:2012 | 03 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,680 | $1,000 | Implemented |
AM0621 # 02 Y:2012 | 02 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,750 | $11,600 | Implemented |
AM0621 # 01 Y:2012 | 01 | 2012 | REPLACE HEAT TREATING OVEN WITH MORE EFFICIENT UNIT | $23,375 | $50,000 | Not Implemented |
MA0699 # 03 Y:2012 | 03 | 2012 | SHUT OFF COOLING IF COLD OUTSIDE AIR WILL COOL PROCESS | $5,019 | $24,000 | Implemented |
MA0699 # 02 Y:2012 | 02 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $19,627 | $104,325 | Implemented |
MA0699 # 05 Y:2012 | 05 | 2012 | USE HEAT PUMP FOR SPACE CONDITIONING | $1,250 | $6,500 | Implemented |
MA0699 # 04 Y:2012 | 04 | 2012 | ELIMINATE/REDUCE AN OPERATION | $1,855 | $500 | Not Implemented |
MA0699 # 01 Y:2012 | 01 | 2012 | INSTALL TIMERS AND/OR THERMOSTATS | $25,140 | $9,900 | Implemented |