IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

26

matching recommendations
Reset
SIC 3674 Semiconductors And Related Devices
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
TP0003 # 06 Y:1999 06 1999 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS $514 $190 Implemented
TP0003 # 05 Y:1999 05 1999 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $387 $12,392 Implemented
TP0003 # 04 Y:1999 04 1999 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $111 $393 Implemented
TP0003 # 03 Y:1999 03 1999 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $642 $20 Implemented
TP0003 # 02 Y:1999 02 1999 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $3,133 $0 Implemented
TP0003 # 01 Y:1999 01 1999 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT $14,358 $14,651 Not Implemented
SD0215 # 02 Y:1999 02 1999 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,635 $6,257 Implemented
SF0161 # 04 Y:1999 04 1999 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT $2,081 $8,340 Not Implemented
SF0161 # 03 Y:1999 03 1999 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT $1,053 $1,408 Not Implemented
SF0161 # 01 Y:1999 01 1999 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $834 $389 Not Implemented
SD0215 # 01 Y:1999 01 1999 INSTALL SPECTRAL REFLECTORS / DELAMP $3,652 $3,480 Not Implemented
SD0215 # 03 Y:1999 03 1999 INSULATE BARE EQUIPMENT $1,080 $906 Not Implemented
SD0215 # 04 Y:1999 04 1999 REDUCE VENTILATION AIR $2,763 $1,600 Not Implemented
SD0215 # 05 Y:1999 05 1999 USE FILTER AND DRYING OVEN TO REDUCE SLUDGE VOLUME $1,153 $3,000 Not Implemented
SD0215 # 06 Y:1999 06 1999 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS $5,300 $7,000 Not Implemented
SD0215 # 07 Y:1999 07 1999 USE LESS TOXIC AND VOLATILE SOLVENT SUBSTITUTES $13,012 $0 Not Implemented
SD0215 # 08 Y:1999 08 1999 REPLACE OLD MACHINE WITH NEW AUTOMATIC MULTI-STATION TOOL $507,180 $5,000 Not Implemented
SF0161 # 02 Y:1999 02 1999 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $1,859 $1,055 Not Implemented
WI0339 # 01 Y:1999 01 1999 SHIFT FROM DAYTIME TO NIGHTTIME OPERATION $3,909 $0 Not Implemented
WI0339 # 02 Y:1999 02 1999 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $245 $300 Implemented
WI0339 # 03 Y:1999 03 1999 LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER $2,824 $1,000 Implemented
WI0339 # 04 Y:1999 04 1999 INSTALL OCCUPANCY SENSORS $1,826 $2,400 Not Implemented
WI0339 # 05 Y:1999 05 1999 DISTILL CONTAMINATED SOLVENTS FOR REUSE $2,534 $4,000 Not Implemented
WI0339 # 06 Y:1999 06 1999 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $1,865 $2,000 Implemented
WI0339 # 07 Y:1999 07 1999 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS $826 $2,600 Not Implemented