Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
502
matching recommendationsSIC | 3679 | Electronic Components, Nec |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MI0451 # 01 Y:2024 | 01 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $10,862 | $16,333 | Implemented |
MI0451 # 04 Y:2024 | 04 | 2024 | OPTIMIZE PLANT POWER FACTOR | $4,130 | $4,044 | Implemented |
MI0451 # 05 Y:2024 | 05 | 2024 | INSTALL OCCUPANCY SENSORS | $2,513 | $1,755 | Implemented |
MI0451 # 06 Y:2024 | 06 | 2024 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $1,231 | $100 | Implemented |
MI0451 # 02 Y:2024 | 02 | 2024 | TURN OFF EQUIPMENT WHEN NOT IN USE | $9,582 | $40 | Implemented |
MI0451 # 07 Y:2024 | 07 | 2024 | INSULATE BARE EQUIPMENT | $529 | $949 | Implemented |
UF0619 # 10 Y:2024 | 10 | 2024 | REPLACE OLD MACHINE WITH NEW AUTOMATIC MULTI-STATION TOOL | $300,000 | $183,056 | Implemented |
UF0619 # 05 Y:2024 | 05 | 2024 | CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD | $3,458 | $9,470 | Implemented |
UF0619 # 01 Y:2024 | 01 | 2024 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $16,482 | $6,000 | Implemented |
UF0619 # 09 Y:2024 | 09 | 2024 | AUTOMATE FINISHING PROCESS | $315,000 | $181,056 | Implemented |
UF0619 # 07 Y:2024 | 07 | 2024 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,007 | $0 | Implemented |
UF0619 # 08 Y:2024 | 08 | 2024 | UPGRADE CONTROLS ON COMPRESSORS | $705 | $1,252 | Implemented |
UF0619 # 03 Y:2024 | 03 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $10,655 | $13,445 | Implemented |
UF0619 # 06 Y:2024 | 06 | 2024 | MINIMIZE CONDENSER COOLING WATER TEMPERATURE | $1,257 | $5,940 | Implemented |
UU0251 # 02 Y:2024 | 02 | 2024 | KEEP DOORS AND WINDOWS SHUT WHEN NOT ON USE | $27,500 | $13,788 | Implemented |
UU0251 # 06 Y:2024 | 06 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,210 | $6,486 | Implemented |
UU0251 # 05 Y:2024 | 05 | 2024 | DEMOLISH OLD BUILDING TO REDUCE TAX AND INSURANCE BILLS | $8,918 | $750 | Implemented |
UU0251 # 01 Y:2024 | 01 | 2024 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $38,394 | $100,000 | Implemented |
OK1113 # 01 Y:2024 | 01 | 2024 | CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS | $3,139 | $4,760 | Implemented |
OK1113 # 02 Y:2024 | 02 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,798 | $1,675 | Implemented |
OK1113 # 05 Y:2024 | 05 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $125 | $611 | Implemented |
MI0434 # 04 Y:2023 | 04 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,225 | $2,000 | Implemented |
MI0434 # 01 Y:2023 | 01 | 2023 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $29,836 | $550 | Implemented |
MI0434 # 08 Y:2023 | 08 | 2023 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,530 | $960 | Implemented |
MI0434 # 03 Y:2023 | 03 | 2023 | TURN OFF EQUIPMENT WHEN NOT IN USE | $14,048 | $0 | Implemented |