Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
126
matching recommendationsSIC | 3679 | Electronic Components, Nec |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UF0619 # 10 Y:2024 | 10 | 2024 | REPLACE OLD MACHINE WITH NEW AUTOMATIC MULTI-STATION TOOL | $300,000 | $183,056 | n/a |
UF0619 # 07 Y:2024 | 07 | 2024 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,007 | $0 | n/a |
UF0619 # 04 Y:2024 | 04 | 2024 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $7,989 | $36,000 | n/a |
UF0619 # 06 Y:2024 | 06 | 2024 | MINIMIZE CONDENSER COOLING WATER TEMPERATURE | $1,257 | $5,940 | n/a |
UF0619 # 03 Y:2024 | 03 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $10,655 | $13,445 | n/a |
UF0619 # 05 Y:2024 | 05 | 2024 | CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD | $3,458 | $9,470 | n/a |
UF0619 # 08 Y:2024 | 08 | 2024 | UPGRADE CONTROLS ON COMPRESSORS | $705 | $1,252 | n/a |
UF0619 # 09 Y:2024 | 09 | 2024 | AUTOMATE FINISHING PROCESS | $315,000 | $181,056 | n/a |
UF0619 # 01 Y:2024 | 01 | 2024 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $16,482 | $6,000 | n/a |
UF0619 # 02 Y:2024 | 02 | 2024 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $11,318 | $25,440 | n/a |
MI0434 # 03 Y:2023 | 03 | 2023 | TURN OFF EQUIPMENT WHEN NOT IN USE | $14,048 | $0 | Implemented |
MI0434 # 07 Y:2023 | 07 | 2023 | INSTALL OCCUPANCY SENSORS | $2,333 | $750 | Not Implemented |
MI0434 # 06 Y:2023 | 06 | 2023 | REPLACE TREATED WATER WITH WELL / SURFACE WATER | $3,200 | $3,460 | Not Implemented |
MI0434 # 05 Y:2023 | 05 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,323 | $7,394 | Implemented |
MI0434 # 08 Y:2023 | 08 | 2023 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,530 | $960 | Implemented |
MI0434 # 02 Y:2023 | 02 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $16,559 | $12,210 | Not Implemented |
MI0434 # 04 Y:2023 | 04 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,225 | $2,000 | Implemented |
MI0434 # 01 Y:2023 | 01 | 2023 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $29,836 | $550 | Implemented |
MI0413 # 06 Y:2022 | 06 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,004 | $1,980 | Implemented |
MI0413 # 07 Y:2022 | 07 | 2022 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $897 | $2,750 | Not Implemented |
MI0413 # 08 Y:2022 | 08 | 2022 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $755 | $645 | Implemented |
MI0413 # 01 Y:2022 | 01 | 2022 | INSTALL PARTITIONS TO REDUCE SIZE OF CONDITIONED SPACE | $7,040 | $10,116 | Not Implemented |
MI0413 # 02 Y:2022 | 02 | 2022 | TURN OFF EQUIPMENT WHEN NOT IN USE | $4,023 | $0 | Implemented |
MI0413 # 03 Y:2022 | 03 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,013 | $5,249 | Implemented |
MI0413 # 04 Y:2022 | 04 | 2022 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $2,034 | $580 | Implemented |