Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
4,221
matching recommendationsSIC | 37 | Transportation Equipment |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
KU0199 # 01 Y:1986 | 01 | 1986 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $8,919 | $6,173 | Implemented |
KU0199 # 03 Y:1986 | 03 | 1986 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $1,330 | $100 | Implemented |
KU0199 # 04 Y:1986 | 04 | 1986 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $1,289 | $100 | Implemented |
KU0199 # 05 Y:1986 | 05 | 1986 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $906 | $34 | Implemented |
KU0199 # 06 Y:1986 | 06 | 1986 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $600 | $200 | Implemented |
UD0193 # 03 Y:1986 | 03 | 1986 | INSTALL SET-BACK TIMERS | $1,589 | $0 | Implemented |
UD0193 # 04 Y:1986 | 04 | 1986 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $3,168 | $0 | Implemented |
UD0193 # 05 Y:1986 | 05 | 1986 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $9,134 | $21,000 | Implemented |
OK0192 # 03 Y:1986 | 03 | 1986 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $10,057 | $3,500 | Implemented |
OK0192 # 05 Y:1986 | 05 | 1986 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $11,547 | $32,800 | Implemented |
OK0192 # 07 Y:1986 | 07 | 1986 | RECOVER AND REUSE COOLING WATER | $96,689 | $52,800 | Implemented |
TN0274 # 04 Y:1986 | 04 | 1986 | INSTALL SET-BACK TIMERS | $227 | $0 | Implemented |
OK0186 # 01 Y:1986 | 01 | 1986 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $678 | $366 | Implemented |
OK0186 # 02 Y:1986 | 02 | 1986 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $46 | $40 | Implemented |
OK0186 # 03 Y:1986 | 03 | 1986 | COVER OPEN TANKS | $3,068 | $829 | Implemented |
OK0186 # 04 Y:1986 | 04 | 1986 | INSTALL / REPAIR INSULATION ON CONDENSATE LINES | $832 | $240 | Implemented |
OK0186 # 05 Y:1986 | 05 | 1986 | REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC | $328 | $83 | Implemented |
CO0050 # 02 Y:1985 | 02 | 1985 | INSTALL TIMERS AND/OR THERMOSTATS | $16,221 | $2,791 | Implemented |
CO0050 # 03 Y:1985 | 03 | 1985 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $888 | $200 | Implemented |
CO0050 # 04 Y:1985 | 04 | 1985 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $159 | $200 | Implemented |
CO0050 # 05 Y:1985 | 05 | 1985 | USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE | $1,313 | $1,600 | Implemented |
CO0050 # 06 Y:1985 | 06 | 1985 | REPLACE BROKEN WINDOWS AND/OR WINDOW SASH | $6,022 | $1,570 | Implemented |
CO0050 # 08 Y:1985 | 08 | 1985 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $2,212 | $800 | Implemented |
AT0031 # 01 Y:1985 | 01 | 1985 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $731 | $1,615 | Implemented |
AT0031 # 02 Y:1985 | 02 | 1985 | INSTALL TIMERS AND/OR THERMOSTATS | $82,865 | $275 | Implemented |