Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
20
matching recommendationsSIC | 37 | Transportation Equipment |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
DL0166 # 01 Y:2016 | 01 | 2016 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,095 | $1,036 | Implemented |
LE0326 # 11 Y:2011 | 11 | 2011 | REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES | $1,230 | $35,000 | Implemented |
LE0326 # 09 Y:2011 | 09 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,818 | $1,000 | Implemented |
LE0326 # 08 Y:2011 | 08 | 2011 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,956 | $25 | Implemented |
LE0326 # 06 Y:2011 | 06 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,255 | $1,000 | Implemented |
LE0326 # 05 Y:2011 | 05 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,890 | $10,580 | Implemented |
LE0326 # 04 Y:2011 | 04 | 2011 | INSTALL TIMERS AND/OR THERMOSTATS | $6,020 | $95 | Implemented |
LE0326 # 03 Y:2011 | 03 | 2011 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $9,313 | $108 | Implemented |
LE0326 # 02 Y:2011 | 02 | 2011 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $10,236 | $51,475 | Implemented |
LE0326 # 01 Y:2011 | 01 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $12,373 | $21,660 | Implemented |
LE0281 # 06 Y:2008 | 06 | 2008 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $923 | $240 | Implemented |
LE0281 # 04 Y:2008 | 04 | 2008 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $1,441 | $2,500 | Implemented |
LE0281 # 02 Y:2008 | 02 | 2008 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $7,477 | $1,790 | Implemented |
LE0152 # 07 Y:2003 | 07 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $28,329 | $57,678 | Implemented |
LE0152 # 06 Y:2003 | 06 | 2003 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $7,694 | $1,312 | Implemented |
LE0152 # 03 Y:2003 | 03 | 2003 | REPLACE BROKEN WINDOWS AND/OR WINDOW SASH | $2,601 | $3,036 | Implemented |
LE0152 # 01 Y:2003 | 01 | 2003 | TURN OFF EQUIPMENT WHEN NOT IN USE | $2,205 | $0 | Implemented |
HO0124 # 04 Y:1995 | 04 | 1995 | USE RADIANT HEATER FOR SPOT HEATING | $714 | $2,400 | Implemented |
HO0124 # 03 Y:1995 | 03 | 1995 | TURN OFF EQUIPMENT WHEN NOT IN USE | $357 | $0 | Implemented |
HO0124 # 01 Y:1995 | 01 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,051 | $11,011 | Implemented |