Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
9,513
matching recommendationsSIC | 37 | Transportation Equipment |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UM0099 # 01 Y:1997 | 01 | 1997 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,644 | $12,823 | Not Implemented |
UM0099 # 02 Y:1997 | 02 | 1997 | INSTALL OCCUPANCY SENSORS | $194 | $200 | Not Implemented |
UM0099 # 03 Y:1997 | 03 | 1997 | REPLACE CITY WATER WITH RECYCLED WATER VIA COOLING TOWER | $5,407 | $4,500 | Not Implemented |
UM0099 # 04 Y:1997 | 04 | 1997 | USE DISTILLATION, EVAPORATION TO REMOVE CONTAMINANTS | $3,527 | $6,000 | Not Implemented |
UM0099 # 05 Y:1997 | 05 | 1997 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $31,291 | $0 | Not Implemented |
WV0128 # 01 Y:1997 | 01 | 1997 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $892 | $150 | Not Implemented |
WV0128 # 02 Y:1997 | 02 | 1997 | CHILL WATER TO THE HIGHEST TEMPERATURE POSSIBLE | $3,725 | $550 | Not Implemented |
WV0128 # 03 Y:1997 | 03 | 1997 | DIRECT WARMEST AIR TO COMBUSTION INTAKE | $2,800 | $4,700 | Not Implemented |
WV0128 # 04 Y:1997 | 04 | 1997 | INSULATE BARE EQUIPMENT | $9,736 | $713 | Not Implemented |
WV0128 # 05 Y:1997 | 05 | 1997 | INSULATE BARE EQUIPMENT | $109 | $33 | Not Implemented |
WV0128 # 06 Y:1997 | 06 | 1997 | USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION | $2,400 | $6,300 | Not Implemented |
WV0128 # 07 Y:1997 | 07 | 1997 | RECOVER AND REUSE COOLING WATER | $2,540 | $9,300 | Not Implemented |
WV0128 # 08 Y:1997 | 08 | 1997 | DEVELOP STANDARD PROCEDURES TO IMPROVE INTERNAL YIELDS | $202,500 | $250,000 | Not Implemented |
MO0213 # 01 Y:1997 | 01 | 1997 | CROSS-TRAIN PERSONNEL TO AVOID LOST TIME | $12,142 | $20,000 | Implemented |
MO0213 # 02 Y:1997 | 02 | 1997 | RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE HANDLING COSTS | $8,250 | $10,000 | Implemented |
MO0213 # 03 Y:1997 | 03 | 1997 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,811 | $10,944 | Not Implemented |
MO0213 # 04 Y:1997 | 04 | 1997 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,904 | $1,046 | Implemented |
MO0213 # 05 Y:1997 | 05 | 1997 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $142 | $414 | Not Implemented |
MO0213 # 06 Y:1997 | 06 | 1997 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,326 | $3,383 | Implemented |
MO0213 # 07 Y:1997 | 07 | 1997 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $6,372 | $80 | Implemented |
MO0213 # 08 Y:1997 | 08 | 1997 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $964 | $180 | Not Implemented |
MO0213 # 09 Y:1997 | 09 | 1997 | UPGRADE OBSOLETE EQUIPMENT | $166,090 | $85,000 | Not Implemented |
MO0213 # 10 Y:1997 | 10 | 1997 | UPGRADE OBSOLETE EQUIPMENT | $4,950 | $6,000 | Implemented |
OR0305 # 01 Y:1997 | 01 | 1997 | REDUCE SCRAP PRODUCTION | $89,400 | $15,300 | Not Implemented |
OR0305 # 02 Y:1997 | 02 | 1997 | USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL | $24,200 | $139,000 | Not Implemented |