Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
9,513
matching recommendationsSIC | 37 | Transportation Equipment |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
GT0625 # 02 Y:1997 | 02 | 1997 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $46,500 | $137,700 | Not Implemented |
GT0625 # 03 Y:1997 | 03 | 1997 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,080 | $400 | Implemented |
GT0625 # 04 Y:1997 | 04 | 1997 | FILTER AND REUSE HYDRAULIC OIL | $19,800 | $7,150 | Implemented |
GT0625 # 05 Y:1997 | 05 | 1997 | REDUCE VENTILATION AIR | $8,640 | $20,000 | Not Implemented |
GT0625 # 06 Y:1997 | 06 | 1997 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,957 | $5,695 | Implemented |
GT0625 # 07 Y:1997 | 07 | 1997 | UTILIZE A CENTRAL COOLANT SYSTEM FOR CLEANING AND REUSE OF METAL WORKING FLUID | $26,000 | $1,780 | Not Implemented |
GT0625 # 08 Y:1997 | 08 | 1997 | MAINTAIN/ENLARGE A STOCK OF SPARE PARTS | $743,700 | $0 | Implemented |
BD0089 # 01 Y:1997 | 01 | 1997 | USE WASTE HEAT FROM FLUE GASES TO HEAT SPACE CONDITIONING AIR | $3,860 | $5,500 | Not Implemented |
BD0089 # 02 Y:1997 | 02 | 1997 | INSTALL PARTITIONS TO REDUCE SIZE OF CONDITIONED SPACE | $3,615 | $1,250 | Not Implemented |
BD0089 # 03 Y:1997 | 03 | 1997 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,151 | $1,151 | Implemented |
BD0089 # 04 Y:1997 | 04 | 1997 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $867 | $325 | Implemented |
BD0089 # 05 Y:1997 | 05 | 1997 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $777 | $0 | Not Implemented |
BD0089 # 06 Y:1997 | 06 | 1997 | INSTALL OCCUPANCY SENSORS | $668 | $525 | Not Implemented |
BD0089 # 07 Y:1997 | 07 | 1997 | RECOVER AND REUSE COOLING WATER | $5,285 | $4,500 | Implemented |
BD0089 # 08 Y:1997 | 08 | 1997 | LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER | $1,881 | $500 | Not Implemented |
BD0089 # 09 Y:1997 | 09 | 1997 | ELIMINATE SHIFT | $22,880 | $2,500 | Implemented |
ND0280 # 01 Y:1997 | 01 | 1997 | CLEAR AND RENT EXISTING SPACE | $160,000 | $5,000 | Not Implemented |
ND0280 # 02 Y:1997 | 02 | 1997 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $10,439 | $8,055 | Implemented |
ND0280 # 03 Y:1997 | 03 | 1997 | USE EVAPORATION TO CONCENTRATE MATERIAL | $6,707 | $10,000 | Not Implemented |
ND0280 # 04 Y:1997 | 04 | 1997 | MODIFY CURRENT INCENTIVE PROGRAM | $5,000 | $176 | Implemented |
ND0280 # 05 Y:1997 | 05 | 1997 | RECOVER WASTE HEAT FROM EQUIPMENT | $3,321 | $2,180 | Not Implemented |
ND0280 # 06 Y:1997 | 06 | 1997 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,854 | $520 | Implemented |
ND0280 # 07 Y:1997 | 07 | 1997 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $1,372 | $220 | Implemented |
ND0280 # 08 Y:1997 | 08 | 1997 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $606 | $1,566 | Implemented |
ND0280 # 09 Y:1997 | 09 | 1997 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $948 | $1,500 | Not Implemented |