Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
9,504
matching recommendationsSIC | 37 | Transportation Equipment |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MI0367 # 07 Y:2020 | 07 | 2020 | REMOVE OR CLOSE OFF UNNEEDED COMPRESSED AIR LINES | $3,190 | $2,500 | Not Implemented |
MI0367 # 08 Y:2020 | 08 | 2020 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,348 | $1,980 | Not Implemented |
UK1916 # 01 Y:2019 | 01 | 2019 | MINIMIZE NON-ESSENTIAL MATERIAL IN HEAT TREATMENT PROCESS | $1,170 | $0 | n/a |
UK1916 # 02 Y:2019 | 02 | 2019 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $18,894 | $0 | n/a |
UK1916 # 03 Y:2019 | 03 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $16,394 | $25,674 | n/a |
UK1916 # 04 Y:2019 | 04 | 2019 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $195 | $75 | n/a |
UK1916 # 05 Y:2019 | 05 | 2019 | AIR CONDITION ONLY SPACE NECESSARY | $4,922 | $11,550 | n/a |
UK1916 # 06 Y:2019 | 06 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $29,402 | $2,614 | n/a |
UK1916 # 07 Y:2019 | 07 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $19,602 | $2,270 | n/a |
UK1916 # 08 Y:2019 | 08 | 2019 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $6,946 | $0 | n/a |
UK1916 # 09 Y:2019 | 09 | 2019 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $86,132 | $206,000 | n/a |
UK1916 # 10 Y:2019 | 10 | 2019 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $139,706 | $225,000 | n/a |
TT0231 # 01 Y:2019 | 01 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $42,957 | $153,710 | Implemented |
TT0231 # 02 Y:2019 | 02 | 2019 | INSTALL COMMON HEADER ON COMPRESSORS | $13,982 | $1,050 | Implemented |
TT0231 # 03 Y:2019 | 03 | 2019 | INSULATE BARE EQUIPMENT | $4,149 | $10,500 | Implemented |
TT0231 # 04 Y:2019 | 04 | 2019 | TURN OFF EQUIPMENT WHEN NOT IN USE | $3,033 | $25 | Implemented |
TT0231 # 05 Y:2019 | 05 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $886 | $40 | Implemented |
TT0231 # 06 Y:2019 | 06 | 2019 | INSTALL OR UPGRADE INSULATION ON HVAC DISTRIBUTION SYSTEMS | $650 | $1,650 | Implemented |
UU0157 # 01 Y:2019 | 01 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $15,321 | $68,567 | Implemented |
UU0157 # 02 Y:2019 | 02 | 2019 | OPTIMIZE PLANT POWER FACTOR | $2,079 | $4,000 | Implemented |
UU0157 # 03 Y:2019 | 03 | 2019 | USE RADIANT HEATER FOR SPOT HEATING | $12,670 | $22,920 | Implemented |
UU0157 # 04 Y:2019 | 04 | 2019 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $9,094 | $8,488 | Implemented |
UU0157 # 05 Y:2019 | 05 | 2019 | TURN OFF EQUIPMENT WHEN NOT IN USE | $314 | $218 | Implemented |
UU0157 # 06 Y:2019 | 06 | 2019 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $3,916 | $3,800 | Implemented |
UU0157 # 07 Y:2019 | 07 | 2019 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $1,880 | $650 | Implemented |