Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
402
matching recommendationsSIC | 37 | Transportation Equipment |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
TT0323 # 07 Y:2025 | 07 | 2025 | AIR CONDITION ONLY SPACE NECESSARY | $12,931 | $18,000 | n/a |
TT0323 # 08 Y:2025 | 08 | 2025 | USE SOLAR HEAT FOR HEAT | $26,365 | $221,500 | n/a |
TT0323 # 06 Y:2025 | 06 | 2025 | UTILIZE OUTSIDE CONTRACTING | $27,937 | $30,000 | n/a |
TT0323 # 05 Y:2025 | 05 | 2025 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,604 | $2,430 | n/a |
TT0323 # 03 Y:2025 | 03 | 2025 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $1,028 | $400 | n/a |
TT0323 # 01 Y:2025 | 01 | 2025 | TURN OFF EQUIPMENT WHEN NOT IN USE | $451 | $0 | n/a |
TT0323 # 04 Y:2025 | 04 | 2025 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $315 | $180 | n/a |
TT0323 # 02 Y:2025 | 02 | 2025 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $8,234 | $2,520 | n/a |
TT0320 # 04 Y:2025 | 04 | 2025 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $18,949 | $23,783 | n/a |
TT0320 # 01 Y:2025 | 01 | 2025 | ADOPT IN-HOUSE MATERIAL GENERATION | $30,976 | $12,000 | n/a |
TT0320 # 02 Y:2025 | 02 | 2025 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,445 | $1,710 | n/a |
TT0320 # 07 Y:2025 | 07 | 2025 | USE SOLAR HEAT TO MAKE ELECTRICTY | $57,337 | $238,118 | n/a |
TT0320 # 03 Y:2025 | 03 | 2025 | RECOVER WASTE HEAT FROM EQUIPMENT | $17,320 | $15,000 | n/a |
TT0320 # 05 Y:2025 | 05 | 2025 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $6,052 | $7,500 | n/a |
TT0320 # 09 Y:2025 | 09 | 2025 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $8,140 | $26,000 | n/a |
TT0320 # 06 Y:2025 | 06 | 2025 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,087 | $6,080 | n/a |
TT0320 # 08 Y:2025 | 08 | 2025 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $12,037 | $75,000 | n/a |
TT0292 # 04 Y:2023 | 04 | 2023 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $6,900 | $600 | Not Implemented |
TT0292 # 05 Y:2023 | 05 | 2023 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $6,004 | $4,240 | Not Implemented |
TT0292 # 01 Y:2023 | 01 | 2023 | USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL | $28,974 | $250 | Not Implemented |
TT0292 # 02 Y:2023 | 02 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $14,314 | $15,941 | Implemented |
TT0292 # 06 Y:2023 | 06 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,057 | $2,190 | Implemented |
TT0292 # 08 Y:2023 | 08 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,268 | $50 | Implemented |
TT0292 # 03 Y:2023 | 03 | 2023 | AIR CONDITION ONLY SPACE NECESSARY | $8,884 | $18,000 | Implemented |
TT0292 # 07 Y:2023 | 07 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,223 | $4,750 | Implemented |