Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
355
matching recommendationsSIC | 37 | Transportation Equipment |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
HO0124 # 02 Y:1995 | 02 | 1995 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $51 | $150 | Not Implemented |
HO0124 # 03 Y:1995 | 03 | 1995 | TURN OFF EQUIPMENT WHEN NOT IN USE | $357 | $0 | Implemented |
HO0124 # 04 Y:1995 | 04 | 1995 | USE RADIANT HEATER FOR SPOT HEATING | $714 | $2,400 | Implemented |
HO0124 # 01 Y:1995 | 01 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,051 | $11,011 | Implemented |
AR0074 # 08 Y:1995 | 08 | 1995 | AVOID INTRODUCING HOT, HUMID, OR DIRTY AIR INTO HVAC SYSTEM | $18,582 | $500 | Implemented |
AR0074 # 07 Y:1995 | 07 | 1995 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $408 | $0 | Implemented |
AR0074 # 10 Y:1995 | 10 | 1995 | MAINTAIN MACHINES TO REDUCE LEAKS | $3,240 | $1,000 | Implemented |
AR0074 # 03 Y:1995 | 03 | 1995 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $9,864 | $350 | Implemented |
AR0074 # 02 Y:1995 | 02 | 1995 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $10,013 | $14,650 | Implemented |
AR0074 # 05 Y:1995 | 05 | 1995 | OPTIMIZE PLANT POWER FACTOR | $5,669 | $13,220 | Not Implemented |
AR0074 # 06 Y:1995 | 06 | 1995 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $139,091 | $55,000 | Not Implemented |
AR0074 # 04 Y:1995 | 04 | 1995 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,547 | $25 | Implemented |
AR0074 # 01 Y:1995 | 01 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $800 | $584 | Implemented |
AR0074 # 09 Y:1995 | 09 | 1995 | TURN OFF EQUIPMENT WHEN NOT IN USE | $2,696 | $200 | Implemented |
GT0565 # 10 Y:1995 | 10 | 1995 | CONVERT TO HIGH VOLUME LOW PRESSURE (HVLP) PAINT GUNS | $272,800 | $20,800 | Not Implemented |
GT0565 # 09 Y:1995 | 09 | 1995 | UPGRADE CONTROLS ON COMPRESSORS | $25,500 | $6,300 | Not Implemented |
GT0565 # 02 Y:1995 | 02 | 1995 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $10,300 | $5,300 | Not Implemented |
GT0565 # 04 Y:1995 | 04 | 1995 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $10,100 | $8,480 | Not Implemented |
GT0565 # 05 Y:1995 | 05 | 1995 | REDUCE COMBUSTION AIR FLOW TO OPTIMUM | $8,570 | $750 | Implemented |
GT0565 # 07 Y:1995 | 07 | 1995 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $3,770 | $320 | Implemented |
GT0565 # 06 Y:1995 | 06 | 1995 | USE SYNTHETIC LUBRICANT | $3,350 | $0 | Not Implemented |
GT0565 # 08 Y:1995 | 08 | 1995 | INSTALL SPECTRAL REFLECTORS / DELAMP | $8,960 | $31,380 | Implemented |
GT0565 # 01 Y:1995 | 01 | 1995 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $10,700 | $85,490 | Implemented |
GT0565 # 03 Y:1995 | 03 | 1995 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,300 | $1,300 | Implemented |
UF0131 # 01 Y:1995 | 01 | 1995 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $6,967 | $13,352 | Implemented |