Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
127
matching recommendationsSIC | 371 | Motor Vehicles And Equipment |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MS0434 # 04 Y:2024 | 04 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $35,214 | $329,875 | n/a |
MS0434 # 01 Y:2024 | 01 | 2024 | INSTALL OCCUPANCY SENSORS | $401 | $879 | n/a |
MS0434 # 02 Y:2024 | 02 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $536 | $1,765 | n/a |
MS0434 # 03 Y:2024 | 03 | 2024 | REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT | $6,585 | $25,000 | n/a |
MS0429 # 01 Y:2024 | 01 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,731 | $8,233 | n/a |
MS0428 # 03 Y:2024 | 03 | 2024 | OPTIMIZE PLANT POWER FACTOR | $788 | $1,677 | n/a |
MS0428 # 02 Y:2024 | 02 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $647 | $0 | n/a |
MS0428 # 01 Y:2024 | 01 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $11,631 | $131,059 | n/a |
MS0429 # 03 Y:2024 | 03 | 2024 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $16,143 | $0 | n/a |
MS0429 # 02 Y:2024 | 02 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $5,847 | $35,728 | n/a |
TT0314 # 02 Y:2024 | 02 | 2024 | REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT | $36,167 | $16,000 | n/a |
TT0314 # 05 Y:2024 | 05 | 2024 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $4,118 | $21,260 | n/a |
TT0314 # 06 Y:2024 | 06 | 2024 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $4,036 | $8,059 | n/a |
TT0314 # 08 Y:2024 | 08 | 2024 | INSTALL SOFT-START TO ELIMINATE NUISANCE TRIPS | $1,111 | $4,500 | n/a |
TT0314 # 03 Y:2024 | 03 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $13,281 | $1,500 | n/a |
TT0314 # 01 Y:2024 | 01 | 2024 | UPGRADE OBSOLETE EQUIPMENT | $51,299 | $312,500 | n/a |
TT0314 # 07 Y:2024 | 07 | 2024 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $2,112 | $0 | n/a |
TT0314 # 04 Y:2024 | 04 | 2024 | SUBSTITUTE COMPRESSED AIR COOLING WITH WATER OR AIR COOLING | $8,319 | $9,842 | n/a |
TT0293 # 06 Y:2023 | 06 | 2023 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $2,199 | $0 | Implemented |
TT0293 # 04 Y:2023 | 04 | 2023 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $6,615 | $31,320 | Implemented |
TT0293 # 07 Y:2023 | 07 | 2023 | INSTALL SOFT-START TO ELIMINATE NUISANCE TRIPS | $923 | $1,600 | Implemented |
TT0293 # 05 Y:2023 | 05 | 2023 | SUBSTITUTE COMPRESSED AIR COOLING WITH WATER OR AIR COOLING | $3,025 | $10,040 | Not Implemented |
TT0293 # 09 Y:2023 | 09 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $630 | $2,000 | Implemented |
TT0293 # 02 Y:2023 | 02 | 2023 | REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT | $10,120 | $0 | Implemented |
TT0293 # 01 Y:2023 | 01 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $20,707 | $1,500 | Implemented |