Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
2,491
matching recommendationsSIC | 372 | Aircraft And Parts |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AS0559 # 05 Y:2023 | 05 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $4,469 | $166 | Not Implemented |
AS0559 # 06 Y:2023 | 06 | 2023 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $4,205 | $248 | Not Implemented |
AS0559 # 07 Y:2023 | 07 | 2023 | INSTALL OCCUPANCY SENSORS | $320 | $235 | Not Implemented |
AS0559 # 08 Y:2023 | 08 | 2023 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $263 | $660 | Not Implemented |
OK1092 # 01 Y:2023 | 01 | 2023 | USE RADIANT HEATER FOR SPOT HEATING | $21,822 | $92,250 | Not Implemented |
OK1092 # 02 Y:2023 | 02 | 2023 | USE PHOTOCELL CONTROLS | $131 | $370 | Not Implemented |
OK1092 # 03 Y:2023 | 03 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $9,058 | $2,490 | Not Implemented |
OK1092 # 04 Y:2023 | 04 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $24,882 | $187,200 | Not Implemented |
OK1095 # 01 Y:2023 | 01 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $35,046 | $25,523 | Implemented |
OK1095 # 02 Y:2023 | 02 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $45,764 | $511,000 | Not Implemented |
OK1095 # 03 Y:2023 | 03 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $19,079 | $1,741 | Implemented |
OK1095 # 04 Y:2023 | 04 | 2023 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $6,550 | $554 | Implemented |
OK1095 # 05 Y:2023 | 05 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $13,655 | $0 | Not Implemented |
OK1095 # 06 Y:2023 | 06 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $17,107 | $15,033 | Implemented |
OK1095 # 07 Y:2023 | 07 | 2023 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $5,622 | $10,410 | Not Implemented |
OK1095 # 08 Y:2023 | 08 | 2023 | COVER OPEN TANKS | $39,010 | $6,977 | Implemented |
TR0043 # 01 Y:2022 | 01 | 2022 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $33,031 | $5,000 | Implemented |
TR0043 # 02 Y:2022 | 02 | 2022 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $34,391 | $20,500 | Not Implemented |
TR0043 # 03 Y:2022 | 03 | 2022 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,725 | $389 | Not Implemented |
NT0010 # 01 Y:2023 | 01 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,307 | $5,753 | Not Implemented |
NT0010 # 02 Y:2023 | 02 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $13,261 | $0 | Not Implemented |
NT0010 # 03 Y:2023 | 03 | 2023 | OPTIMIZE PLANT POWER FACTOR | $4,823 | $5,241 | Not Implemented |
NT0010 # 04 Y:2023 | 04 | 2023 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $37,440 | $111,000 | Not Implemented |
NT0010 # 05 Y:2023 | 05 | 2023 | CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD | $1,400 | $1,600 | Not Implemented |
NT0010 # 06 Y:2023 | 06 | 2023 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $1,423 | $0 | Not Implemented |