Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
98
matching recommendationsSIC | 372 | Aircraft And Parts |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OK0802 # 01 Y:2010 | 01 | 2010 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $10,017 | $6,215 | Not Implemented |
OK0802 # 09 Y:2010 | 09 | 2010 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $11,625 | $0 | Implemented |
OK0802 # 07 Y:2010 | 07 | 2010 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $30,411 | $45,000 | Implemented |
OK0802 # 08 Y:2010 | 08 | 2010 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $23,800 | $15,600 | Implemented |
OK0802 # 03 Y:2010 | 03 | 2010 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $3,477 | $2,599 | Not Implemented |
OK0802 # 05 Y:2010 | 05 | 2010 | REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC | $11,414 | $51,875 | Implemented |
OK0802 # 06 Y:2010 | 06 | 2010 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $10,918 | $2,775 | Implemented |
OK0802 # 04 Y:2010 | 04 | 2010 | INSTALL OCCUPANCY SENSORS | $1,998 | $13,149 | Implemented |
OK0802 # 10 Y:2010 | 10 | 2010 | COMBINE UTILITY METERS | $936 | $175 | Implemented |
OK0802 # 02 Y:2010 | 02 | 2010 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $8,400 | $1,550 | Implemented |
OK0801 # 11 Y:2010 | 11 | 2010 | OPTIMIZE PLANT POWER FACTOR | $669 | $9,307 | Not Implemented |
OK0801 # 12 Y:2010 | 12 | 2010 | SHUT OFF COOLING IF COLD OUTSIDE AIR WILL COOL PROCESS | $4,196 | $21,075 | Implemented |
OK0801 # 10 Y:2010 | 10 | 2010 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $7,069 | $14,336 | Not Implemented |
OK0801 # 02 Y:2010 | 02 | 2010 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $4,599 | $34,948 | Implemented |
OK0801 # 09 Y:2010 | 09 | 2010 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $299 | $201 | Not Implemented |
OK0801 # 08 Y:2010 | 08 | 2010 | INSTALL OCCUPANCY SENSORS | $547 | $1,658 | Not Implemented |
OK0801 # 07 Y:2010 | 07 | 2010 | RECOVER WASTE HEAT FROM EQUIPMENT | $3,015 | $2,017 | Not Implemented |
OK0801 # 06 Y:2010 | 06 | 2010 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $523 | $516 | Not Implemented |
OK0801 # 05 Y:2010 | 05 | 2010 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,205 | $660 | Not Implemented |
OK0801 # 04 Y:2010 | 04 | 2010 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $995 | $2,625 | Implemented |
OK0801 # 03 Y:2010 | 03 | 2010 | CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS | $9,699 | $3,000 | Implemented |
OK0801 # 01 Y:2010 | 01 | 2010 | USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE | $6,511 | $78,169 | Implemented |
CO0644 # 06 Y:2010 | 06 | 2010 | REDUCE VENTILATION AIR | $1,390 | $12,400 | Implemented |
CO0644 # 05 Y:2010 | 05 | 2010 | USE SOLAR HEAT TO MAKE ELECTRICTY | $2,500 | $27,500 | Not Implemented |
CO0644 # 02 Y:2010 | 02 | 2010 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $14,750 | $1,000 | Implemented |