Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
588
matching recommendationsSIC | 3724 | Aircraft Engines And Engine Parts |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UF0110 # 03 Y:1995 | 03 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $230 | $400 | Implemented |
UF0110 # 04 Y:1995 | 04 | 1995 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $25,754 | $0 | Not Implemented |
UF0110 # 05 Y:1995 | 05 | 1995 | REPLACE ELECTRIC REHEAT WITH HEAT PIPES | $19,763 | $21,000 | Not Implemented |
UF0110 # 06 Y:1995 | 06 | 1995 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $95 | $284 | Not Implemented |
UD0414 # 01 Y:1993 | 01 | 1993 | PAY UTILITY BILLS ON TIME | $2,100 | $0 | Implemented |
UD0414 # 02 Y:1993 | 02 | 1993 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $20,700 | $20,000 | Not Implemented |
UD0414 # 03 Y:1993 | 03 | 1993 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,246 | $14,248 | Implemented |
UD0414 # 04 Y:1993 | 04 | 1993 | INSTALL SET-BACK TIMERS | $1,773 | $500 | Implemented |
UD0414 # 05 Y:1993 | 05 | 1993 | INSTALL SET-BACK TIMERS | $1,689 | $1,500 | Implemented |
UD0414 # 06 Y:1993 | 06 | 1993 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $3,519 | $0 | Not Implemented |
MA0277 # 01 Y:1993 | 01 | 1993 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $39,298 | $39,650 | Implemented |
MA0277 # 02 Y:1993 | 02 | 1993 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $5,123 | $3,800 | Implemented |
MA0277 # 03 Y:1993 | 03 | 1993 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,443 | $5,557 | Implemented |
MA0277 # 04 Y:1993 | 04 | 1993 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,397 | $91 | Implemented |
MA0277 # 05 Y:1993 | 05 | 1993 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $784 | $180 | Implemented |
MA0277 # 06 Y:1993 | 06 | 1993 | INSTALL / REPAIR INSULATION ON CONDENSATE LINES | $550 | $126 | Not Implemented |
TN0482 # 01 Y:1993 | 01 | 1993 | INSTALL SPECTRAL REFLECTORS / DELAMP | $18,977 | $30,900 | n/a |
TN0482 # 02 Y:1993 | 02 | 1993 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,459 | $1,504 | n/a |
TN0482 # 03 Y:1993 | 03 | 1993 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $5,234 | $600 | n/a |
TN0482 # 04 Y:1993 | 04 | 1993 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $923 | $185 | n/a |
TN0482 # 05 Y:1993 | 05 | 1993 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $277 | $720 | n/a |
TN0482 # 06 Y:1993 | 06 | 1993 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $10,141 | $0 | n/a |
ND0033 # 01 Y:1992 | 01 | 1992 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,764 | $7,603 | Not Implemented |
ND0033 # 02 Y:1992 | 02 | 1992 | OPTIMIZE PLANT POWER FACTOR | $10,415 | $20,070 | Implemented |
ND0033 # 03 Y:1992 | 03 | 1992 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,659 | $8,523 | Not Implemented |