Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
257
matching recommendationsSIC | 3732 | Boat Building And Repairing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MU0041 # 03 Y:2023 | 03 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $26,806 | $25,843 | Implemented |
MU0041 # 07 Y:2023 | 07 | 2023 | INSTALL SET-BACK TIMERS | $86,283 | $371,500 | Implemented |
MU0041 # 08 Y:2023 | 08 | 2023 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $3,605 | $0 | Implemented |
MU0041 # 04 Y:2023 | 04 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $11,396 | $6,403 | Implemented |
MU0041 # 05 Y:2023 | 05 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $673 | $240 | Implemented |
MU0041 # 12 Y:2023 | 12 | 2023 | UTILIZE SENSORS CONTROLLING ROOF AND WALL OPENINGS | $4,105 | $5,076 | Implemented |
MU0041 # 01 Y:2023 | 01 | 2023 | INSTALL AUTOMATIC STACK DAMPER | $4,161 | $959 | Implemented |
MU0041 # 06 Y:2023 | 06 | 2023 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $20,235 | $100,548 | Implemented |
MZ0306 # 04 Y:2022 | 04 | 2022 | INSTALL OCCUPANCY SENSORS | $247 | $870 | Implemented |
TT0270 # 01 Y:2022 | 01 | 2022 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $10,427 | $2,000 | Implemented |
TT0270 # 02 Y:2022 | 02 | 2022 | TURN OFF EQUIPMENT WHEN NOT IN USE | $5,525 | $50 | Implemented |
TT0270 # 03 Y:2022 | 03 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,877 | $2,770 | Implemented |
OK1067 # 04 Y:2022 | 04 | 2022 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,861 | $0 | Implemented |
OK1067 # 02 Y:2022 | 02 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,849 | $11,877 | Implemented |
OK1067 # 01 Y:2022 | 01 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $25,333 | $81,525 | Implemented |
OK1067 # 06 Y:2022 | 06 | 2022 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $12,100 | $0 | Implemented |
GT0935 # 02 Y:2019 | 02 | 2019 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $154 | $260 | Implemented |
CL1904 # 02 Y:2019 | 02 | 2019 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $2,689 | $0 | Implemented |
CL1904 # 01 Y:2019 | 01 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $35,719 | $44,796 | Implemented |
CL1904 # 03 Y:2019 | 03 | 2019 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $13,034 | $38,500 | Implemented |
BS0098 # 05 Y:2017 | 05 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $345 | $412 | Implemented |
BS0098 # 06 Y:2017 | 06 | 2017 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $148 | $480 | Implemented |
BS0098 # 07 Y:2017 | 07 | 2017 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $48 | $15 | Implemented |
BS0098 # 09 Y:2017 | 09 | 2017 | DISCONNECT BALLASTS | $21 | $15 | Implemented |
BS0098 # 10 Y:2017 | 10 | 2017 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $1,240 | $400 | Implemented |