Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
13
matching recommendationsSIC | 3769 | Space Vehicle Equipment, Nec |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
LM0102 # 01 Y:2005 | 01 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,202 | $500 | Implemented |
LM0102 # 02 Y:2005 | 02 | 2005 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,058 | $1,000 | Implemented |
LM0102 # 03 Y:2005 | 03 | 2005 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $3,712 | $200 | Implemented |
LM0102 # 04 Y:2005 | 04 | 2005 | PURCHASE NEW EQUIPMENT TO REDUCE MATERIAL USE / COST | $450,000 | $15,000 | Not Implemented |
LM0102 # 05 Y:2005 | 05 | 2005 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $1,258,000 | $1,250,000 | Implemented |
MS0276 # 01 Y:2005 | 01 | 2005 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $64,043 | $8,505 | Not Implemented |
MS0276 # 02 Y:2005 | 02 | 2005 | INSTALL OCCUPANCY SENSORS | $32,940 | $298 | Not Implemented |
MS0276 # 03 Y:2005 | 03 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $20,566 | $20,159 | Implemented |
MS0276 # 04 Y:2005 | 04 | 2005 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $16,492 | $8,838 | Not Implemented |
MS0276 # 05 Y:2005 | 05 | 2005 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $6,547 | $15,656 | Not Implemented |
MS0276 # 06 Y:2005 | 06 | 2005 | USE SEPARATE SWITCHES ON PERIMETER LIGHTING WHICH MAY BE TURNED OFF WHEN NATURAL LIGHT IS AVAILABLE | $2,712 | $1,848 | Not Implemented |
MS0276 # 07 Y:2005 | 07 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,158 | $1,871 | Implemented |
MS0276 # 08 Y:2005 | 08 | 2005 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $398 | $478 | Not Implemented |