Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,872
matching recommendationsSIC | 38 | Instruments And Related Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AM0069 # 04 Y:1989 | 04 | 1989 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,360 | $1,000 | Implemented |
AM0070 # 03 Y:1989 | 03 | 1989 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $175 | $250 | Implemented |
AM0070 # 05 Y:1989 | 05 | 1989 | CENTRALIZE CONTROL OF EXHAUST FANS TO ENSURE THEIR SHUTDOWN, OR ESTABLISH PROGRAM TO ENSURE MANUAL SHUTDOWN | $120 | $0 | Implemented |
TN0374 # 01 Y:1989 | 01 | 1989 | INSTALL TIMERS AND/OR THERMOSTATS | $3,618 | $3,660 | Implemented |
TN0374 # 02 Y:1989 | 02 | 1989 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,973 | $840 | Implemented |
TN0374 # 04 Y:1989 | 04 | 1989 | IMPROVE LUBRICATION PRACTICES | $2,011 | $600 | Implemented |
TN0374 # 07 Y:1989 | 07 | 1989 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $813 | $1,250 | Implemented |
TN0366 # 01 Y:1989 | 01 | 1989 | USE MINIMUM STEAM OPERATING PRESSURE | $4,924 | $0 | Implemented |
TN0366 # 02 Y:1989 | 02 | 1989 | REPAIR AND ELIMINATE STEAM LEAKS | $4,213 | $720 | Implemented |
TN0366 # 03 Y:1989 | 03 | 1989 | INSTALL / REPAIR INSULATION ON STEAM LINES | $2,450 | $718 | Implemented |
TN0366 # 05 Y:1989 | 05 | 1989 | INCREASE AMOUNT OF CONDENSATE RETURNED | $1,712 | $4,156 | Implemented |
TN0366 # 06 Y:1989 | 06 | 1989 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $8,977 | $330 | Implemented |
TN0366 # 08 Y:1989 | 08 | 1989 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $556 | $0 | Implemented |
TN0366 # 09 Y:1989 | 09 | 1989 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $4,404 | $4,000 | Implemented |
TN0366 # 10 Y:1989 | 10 | 1989 | INSULATE BARE EQUIPMENT | $123 | $50 | Implemented |
MA0148 # 09 Y:1989 | 09 | 1989 | INSULATE BARE EQUIPMENT | $1,186 | $316 | Implemented |
MA0148 # 03 Y:1989 | 03 | 1989 | USE HOT PROCESS FLUIDS TO PREHEAT INCOMING PROCESS FLUIDS | $6,780 | $7,000 | Implemented |
MA0148 # 07 Y:1989 | 07 | 1989 | REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC | $3,059 | $2,300 | Implemented |
MA0148 # 08 Y:1989 | 08 | 1989 | INSTALL / REPAIR INSULATION ON STEAM LINES | $668 | $529 | Implemented |
CO0148 # 01 Y:1989 | 01 | 1989 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $490 | $850 | Implemented |
CO0148 # 02 Y:1989 | 02 | 1989 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $3,360 | $250 | Implemented |
CO0148 # 03 Y:1989 | 03 | 1989 | REDUCE VENTILATION AIR | $2,010 | $1,700 | Implemented |
GT0356 # 01 Y:1988 | 01 | 1988 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $11,680 | $32,200 | Implemented |
GT0356 # 03 Y:1988 | 03 | 1988 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $5,859 | $8,805 | Implemented |
GT0356 # 04 Y:1988 | 04 | 1988 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,430 | $1,000 | Implemented |