Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
194
matching recommendationsSIC | 381 | Search And Navigation Equipment |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SF0215 # 06 Y:2001 | 06 | 2001 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $2,758 | $3,291 | Implemented |
SF0215 # 07 Y:2001 | 07 | 2001 | INSTALL OCCUPANCY SENSORS | $6,547 | $14,341 | Implemented |
SF0215 # 08 Y:2001 | 08 | 2001 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $5,806 | $14,760 | n/a |
SF0215 # 09 Y:2001 | 09 | 2001 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $1,329 | $3,400 | Not Implemented |
SF0215 # 10 Y:2001 | 10 | 2001 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $33,374 | $128,000 | n/a |
SF0215 # 11 Y:2001 | 11 | 2001 | USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL | $219,121 | $0 | Implemented |
SF0215 # 12 Y:2001 | 12 | 2001 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $3,216 | $0 | Not Implemented |
SF0215 # 13 Y:2001 | 13 | 2001 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $461,186 | $60,000 | n/a |
SF0215 # 14 Y:2001 | 14 | 2001 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $139,058 | $35,200 | n/a |
SF0215 # 15 Y:2001 | 15 | 2001 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $5,003 | $5,111 | Implemented |
LM0005 # 01 Y:2001 | 01 | 2001 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $635 | $100 | Implemented |
LM0005 # 02 Y:2001 | 02 | 2001 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $587 | $115 | Implemented |
LM0005 # 03 Y:2001 | 03 | 2001 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $25,900 | $12,500 | Not Implemented |
LM0005 # 04 Y:2001 | 04 | 2001 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $3,600 | $0 | Not Implemented |
LM0005 # 05 Y:2001 | 05 | 2001 | TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY | $168,480 | $45,830 | Not Implemented |
LM0005 # 06 Y:2001 | 06 | 2001 | DEVELOP STANDARD PROCEDURES TO IMPROVE INTERNAL YIELDS | $6,000 | $5,000 | Not Implemented |
MS0177 # 01 Y:2001 | 01 | 2001 | USE SEPARATE SWITCHES ON PERIMETER LIGHTING WHICH MAY BE TURNED OFF WHEN NATURAL LIGHT IS AVAILABLE | $3,133 | $630 | Implemented |
MS0177 # 02 Y:2001 | 02 | 2001 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $196 | $209 | Implemented |
MS0177 # 03 Y:2001 | 03 | 2001 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,066 | $3,354 | Not Implemented |
HO0207 # 01 Y:1999 | 01 | 1999 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $28,880 | $600 | Implemented |
HO0207 # 02 Y:1999 | 02 | 1999 | TURN OFF EQUIPMENT WHEN NOT IN USE | $11,756 | $15,000 | Implemented |
HO0207 # 03 Y:1999 | 03 | 1999 | INSTALL OCCUPANCY SENSORS | $5,242 | $10,000 | Implemented |
HO0207 # 04 Y:1999 | 04 | 1999 | TURN OFF EQUIPMENT WHEN NOT IN USE | $2,590 | $0 | Implemented |
HO0207 # 05 Y:1999 | 05 | 1999 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $590 | $0 | Implemented |
HO0207 # 06 Y:1999 | 06 | 1999 | TURN OFF EQUIPMENT WHEN NOT IN USE | $1,738 | $0 | Not Implemented |