Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
276
matching recommendationsSIC | 382 | Measuring And Controlling Devices |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SF0441 # 01 Y:2013 | 01 | 2013 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $27,444 | $0 | Implemented |
SD0460 # 03 Y:2013 | 03 | 2013 | TURN OFF EQUIPMENT WHEN NOT IN USE | $11,357 | $1,000 | Implemented |
SD0460 # 01 Y:2013 | 01 | 2013 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $50,132 | $152,300 | Implemented |
SD0460 # 02 Y:2013 | 02 | 2013 | CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD | $48,502 | $119,500 | Not Implemented |
SD0460 # 04 Y:2013 | 04 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,875 | $900 | Implemented |
SD0460 # 05 Y:2013 | 05 | 2013 | REPLACE BOILER | $4,735 | $14,250 | Not Implemented |
SD0460 # 06 Y:2013 | 06 | 2013 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,847 | $7,050 | Not Implemented |
SD0460 # 07 Y:2013 | 07 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,515 | $3,212 | Implemented |
SD0460 # 08 Y:2013 | 08 | 2013 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,570 | $200 | Implemented |
SD0460 # 09 Y:2013 | 09 | 2013 | USE PHOTOCELL CONTROLS | $1,249 | $1,100 | Not Implemented |
SD0460 # 10 Y:2013 | 10 | 2013 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $731 | $2,500 | Implemented |
SD0439 # 01 Y:2011 | 01 | 2011 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,054 | $100 | Not Implemented |
SD0439 # 02 Y:2011 | 02 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,678 | $700 | Not Implemented |
SD0439 # 03 Y:2011 | 03 | 2011 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $16,510 | $5,375 | Not Implemented |
SD0439 # 04 Y:2011 | 04 | 2011 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $5,851 | $8,326 | Not Implemented |
SD0439 # 05 Y:2011 | 05 | 2011 | USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT | $110,990 | $185,200 | Not Implemented |
SD0439 # 06 Y:2011 | 06 | 2011 | RECOVER WASTE HEAT FROM EQUIPMENT | $163,156 | $302,600 | Not Implemented |
SD0438 # 04 Y:2011 | 04 | 2011 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $28,654 | $53,450 | Not Implemented |
SD0438 # 05 Y:2011 | 05 | 2011 | OPTIMIZE PLANT POWER FACTOR | $12,712 | $37,600 | Implemented |
SD0438 # 06 Y:2011 | 06 | 2011 | INSTALL SKYLIGHTS | $8,562 | $25,530 | Not Implemented |
SD0438 # 03 Y:2011 | 03 | 2011 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $1,445 | $1,530 | Not Implemented |
SD0438 # 02 Y:2011 | 02 | 2011 | COVER OPEN TANKS | $36,210 | $16,850 | Not Implemented |
SD0438 # 01 Y:2011 | 01 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,004 | $300 | Implemented |
SD0407 # 05 Y:2008 | 05 | 2008 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,341 | $1,374 | Implemented |
SD0407 # 06 Y:2008 | 06 | 2008 | INSTALL SKYLIGHTS | $990 | $2,940 | Not Implemented |