IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

54

matching recommendations
Reset
SIC 382 Measuring And Controlling Devices
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
OK1066 # 03 Y:2022 03 2022 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $5,177 $23,400 Implemented
OK1066 # 02 Y:2022 02 2022 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $2,182 $0 Not Implemented
OK1066 # 01 Y:2022 01 2022 OPTIMIZE PLANT POWER FACTOR $3,854 $7,908 Not Implemented
OK1066 # 06 Y:2022 06 2022 USE SOLAR HEAT TO MAKE ELECTRICTY $13,995 $191,438 Not Implemented
OK1066 # 05 Y:2022 05 2022 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS $7,555 $0 Implemented
OK1066 # 04 Y:2022 04 2022 CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES $399 $510 Not Implemented
OK0665 # 09 Y:2003 09 2003 CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD $7,136 $32,000 n/a
OK0665 # 08 Y:2003 08 2003 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,270 $1,048 Implemented
OK0665 # 07 Y:2003 07 2003 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $5,550 $13,880 Implemented
OK0665 # 06 Y:2003 06 2003 INSTALL OCCUPANCY SENSORS $1,398 $1,374 Not Implemented
OK0665 # 05 Y:2003 05 2003 $10,600 $0 Implemented
OK0665 # 04 Y:2003 04 2003 INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT $2,748 $3,480 Implemented
OK0665 # 03 Y:2003 03 2003 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $2,094 $6,844 Not Implemented
OK0665 # 01 Y:2003 01 2003 INSTALL SET-BACK TIMERS $4,895 $664 Implemented
OK0665 # 02 Y:2003 02 2003 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $2,602 $0 Not Implemented
OK0396 # 03 Y:1993 03 1993 INSTALL SET-BACK TIMERS $1,153 $570 Not Implemented
OK0396 # 06 Y:1993 06 1993 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $511 $0 Not Implemented
OK0396 # 05 Y:1993 05 1993 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $286 $0 Implemented
OK0396 # 04 Y:1993 04 1993 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $904 $270 Implemented
OK0396 # 01 Y:1993 01 1993 USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING $3,199 $8,100 Implemented
OK0396 # 02 Y:1993 02 1993 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,139 $80 Implemented
OK0396 # 07 Y:1993 07 1993 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $240 $897 Implemented
OK0391 # 06 Y:1992 06 1992 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT $3,908 $4,518 Not Implemented
OK0391 # 05 Y:1992 05 1992 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $966 $1,880 Implemented
OK0391 # 02 Y:1992 02 1992 KEEP LAMPS AND REFLECTORS CLEAN $2,101 $4,704 Not Implemented