Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,840
matching recommendationsSIC | 384 | Medical Instruments And Supplies |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
CO0148 # 01 Y:1989 | 01 | 1989 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $490 | $850 | Implemented |
CO0148 # 02 Y:1989 | 02 | 1989 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $3,360 | $250 | Implemented |
CO0148 # 03 Y:1989 | 03 | 1989 | REDUCE VENTILATION AIR | $2,010 | $1,700 | Implemented |
CO0148 # 04 Y:1989 | 04 | 1989 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $580 | $0 | Not Implemented |
MA0131 # 01 Y:1988 | 01 | 1988 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $749 | $1,042 | Implemented |
MA0131 # 02 Y:1988 | 02 | 1988 | DE-ENERGIZE EXCESS TRANSFORMER CAPACITY | $604 | $1,292 | Not Implemented |
MA0131 # 03 Y:1988 | 03 | 1988 | INSULATE BARE EQUIPMENT | $435 | $161 | Implemented |
MA0131 # 04 Y:1988 | 04 | 1988 | INSTALL / REPAIR INSULATION ON STEAM LINES | $449 | $324 | Implemented |
MA0131 # 05 Y:1988 | 05 | 1988 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $876 | $3,000 | Implemented |
GT0356 # 01 Y:1988 | 01 | 1988 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $11,680 | $32,200 | Implemented |
GT0356 # 02 Y:1988 | 02 | 1988 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $3,342 | $3,313 | Not Implemented |
GT0356 # 03 Y:1988 | 03 | 1988 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $5,859 | $8,805 | Implemented |
GT0356 # 04 Y:1988 | 04 | 1988 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,430 | $1,000 | Implemented |
GT0356 # 05 Y:1988 | 05 | 1988 | IMPROVE LUBRICATION PRACTICES | $10,600 | $1,830 | Implemented |
GT0356 # 06 Y:1988 | 06 | 1988 | USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE | $27,600 | $10,000 | Not Implemented |
LT0129 # 01 Y:1988 | 01 | 1988 | INSULATE BARE EQUIPMENT | $6,480 | $5,500 | Implemented |
LT0129 # 02 Y:1988 | 02 | 1988 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $500 | $0 | Not Implemented |
LT0129 # 03 Y:1988 | 03 | 1988 | RECOVER WASTE HEAT FROM EQUIPMENT | $3,300 | $7,900 | Not Implemented |
LT0129 # 04 Y:1988 | 04 | 1988 | USE RADIANT HEATER FOR SPOT HEATING | $9,900 | $5,000 | Not Implemented |
LT0129 # 05 Y:1988 | 05 | 1988 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $4,520 | $5,557 | Implemented |
LT0129 # 06 Y:1988 | 06 | 1988 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $7,020 | $0 | Implemented |
LT0129 # 07 Y:1988 | 07 | 1988 | AIR CONDITION ONLY SPACE NECESSARY | $6,100 | $6,000 | Not Implemented |
LT0129 # 08 Y:1988 | 08 | 1988 | INSTALL TIMERS AND/OR THERMOSTATS | $590 | $600 | Not Implemented |
LT0129 # 09 Y:1988 | 09 | 1988 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $53 | $55 | Implemented |
OR0020 # 01 Y:1988 | 01 | 1988 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $11,310 | $0 | Not Implemented |