Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,007
matching recommendationsSIC | 3841 | Surgical And Medical Instruments |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MI0437 # 05 Y:2023 | 05 | 2023 | INSTALL OCCUPANCY SENSORS | $441 | $433 | n/a |
UC2316 # 04 Y:2023 | 04 | 2023 | INSTALL TURBULATORS | $13,337 | $10,920 | n/a |
UC2316 # 09 Y:2023 | 09 | 2023 | INSTALL WIND POWERED ELECTRIC GENERATOR | $1,380,736 | $10,992,131 | n/a |
UC2316 # 10 Y:2023 | 10 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $20,195 | $268,543 | n/a |
UC2316 # 02 Y:2023 | 02 | 2023 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $7,167 | $5,801 | n/a |
UC2316 # 08 Y:2023 | 08 | 2023 | BURN FOSSIL FUEL TO PRODUCE STEAM TO DRIVE A STEAM TURBINE-GENERATOR AND USE STEAM EXHAUST FOR HEAT | $22,194 | $134,412 | n/a |
UC2316 # 06 Y:2023 | 06 | 2023 | BURN A LESS EXPENSIVE GRADE OF FUEL | $153,910 | $207,578 | n/a |
UC2316 # 03 Y:2023 | 03 | 2023 | RECOVER AND REUSE WASTE MATERIAL | $76,811 | $332,613 | n/a |
UC2316 # 07 Y:2023 | 07 | 2023 | REPLACE BOILER | $177,614 | $423,535 | n/a |
UC2316 # 01 Y:2023 | 01 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $26,355 | $75 | n/a |
UC2316 # 05 Y:2023 | 05 | 2023 | REDUCE EXCESSIVE BOILER BLOWDOWN | $2,801 | $12,000 | n/a |
MI0429 # 01 Y:2023 | 01 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $172,404 | $974,914 | Not Implemented |
MI0429 # 02 Y:2023 | 02 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $31,739 | $1,660 | Implemented |
MI0429 # 03 Y:2023 | 03 | 2023 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $25,267 | $0 | Not Implemented |
MI0429 # 04 Y:2023 | 04 | 2023 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $16,344 | $70,840 | Not Implemented |
MI0429 # 05 Y:2023 | 05 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,166 | $12,997 | Implemented |
MI0429 # 06 Y:2023 | 06 | 2023 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $4,831 | $6,950 | Not Implemented |
MI0429 # 07 Y:2023 | 07 | 2023 | USE SOLAR HEAT TO HEAT WATER | $1,687 | $8,166 | Not Implemented |
MI0429 # 08 Y:2023 | 08 | 2023 | INSULATE BARE EQUIPMENT | $1,608 | $1,012 | Not Implemented |
UU0231 # 04 Y:2023 | 04 | 2023 | UTILIZE AN EVAPORATIVE AIR PRE-COOLER OR OTHER HEAT EXCHANGER IN AC SYSTEM | $6,026 | $30,128 | Not Implemented |
UU0231 # 05 Y:2023 | 05 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $15,898 | $263,547 | Implemented |
UU0231 # 02 Y:2023 | 02 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $14,519 | $14,890 | Implemented |
UU0231 # 03 Y:2023 | 03 | 2023 | VENTILATION SYSTEM TO SHUT OFF WHEN ROOM IS NOT IN USE | $6,518 | $19,160 | Implemented |
UU0231 # 01 Y:2023 | 01 | 2023 | STORE HEATED/ COOLED WATER FOR USE DURING PEAK DEMAND PERIODS | $19,636 | $127,500 | Not Implemented |
SU0533 # 04 Y:2023 | 04 | 2023 | DISCONNECT BALLASTS | $8,707 | $0 | n/a |