Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
130
matching recommendationsSIC | 3841 | Surgical And Medical Instruments |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MI0437 # 01 Y:2023 | 01 | 2023 | USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT | $595,572 | $1,797,720 | Not Implemented |
MI0437 # 02 Y:2023 | 02 | 2023 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $127,058 | $120 | Implemented |
MI0437 # 03 Y:2023 | 03 | 2023 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $92,403 | $2,400 | Not Implemented |
MI0437 # 04 Y:2023 | 04 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $28,425 | $24,780 | Not Implemented |
MI0437 # 05 Y:2023 | 05 | 2023 | INSTALL OCCUPANCY SENSORS | $441 | $433 | Implemented |
UC2316 # 01 Y:2023 | 01 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $26,355 | $75 | Not Implemented |
UC2316 # 02 Y:2023 | 02 | 2023 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $7,167 | $5,801 | Not Implemented |
UC2316 # 03 Y:2023 | 03 | 2023 | RECOVER AND REUSE WASTE MATERIAL | $76,811 | $332,613 | Not Implemented |
UC2316 # 04 Y:2023 | 04 | 2023 | INSTALL TURBULATORS | $13,337 | $10,920 | Not Implemented |
UC2316 # 05 Y:2023 | 05 | 2023 | REDUCE EXCESSIVE BOILER BLOWDOWN | $2,801 | $12,000 | Not Implemented |
UC2316 # 10 Y:2023 | 10 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $20,195 | $268,543 | Not Implemented |
UC2316 # 09 Y:2023 | 09 | 2023 | INSTALL WIND POWERED ELECTRIC GENERATOR | $1,380,736 | $10,992,131 | Not Implemented |
UC2316 # 08 Y:2023 | 08 | 2023 | BURN FOSSIL FUEL TO PRODUCE STEAM TO DRIVE A STEAM TURBINE-GENERATOR AND USE STEAM EXHAUST FOR HEAT | $22,194 | $134,412 | Not Implemented |
UC2316 # 07 Y:2023 | 07 | 2023 | REPLACE BOILER | $177,614 | $423,535 | Not Implemented |
UC2316 # 06 Y:2023 | 06 | 2023 | BURN A LESS EXPENSIVE GRADE OF FUEL | $153,910 | $207,578 | Not Implemented |
MI0429 # 01 Y:2023 | 01 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $172,404 | $974,914 | Not Implemented |
MI0429 # 02 Y:2023 | 02 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $31,739 | $1,660 | Implemented |
MI0429 # 03 Y:2023 | 03 | 2023 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $25,267 | $0 | Not Implemented |
MI0429 # 04 Y:2023 | 04 | 2023 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $16,344 | $70,840 | Not Implemented |
MI0429 # 05 Y:2023 | 05 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,166 | $12,997 | Implemented |
MI0429 # 06 Y:2023 | 06 | 2023 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $4,831 | $6,950 | Not Implemented |
MI0429 # 07 Y:2023 | 07 | 2023 | USE SOLAR HEAT TO HEAT WATER | $1,687 | $8,166 | Not Implemented |
MI0429 # 08 Y:2023 | 08 | 2023 | INSULATE BARE EQUIPMENT | $1,608 | $1,012 | Not Implemented |
UU0231 # 05 Y:2023 | 05 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $15,898 | $263,547 | Implemented |
UU0231 # 02 Y:2023 | 02 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $14,519 | $14,890 | Implemented |