Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
21
matching recommendationsSIC | 3842 | Surgical Appliances And Supplies |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MI0233 # 02 Y:2012 | 02 | 2012 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $150,126 | $80 | Implemented |
MI0233 # 12 Y:2012 | 12 | 2012 | MAINTAIN AIR FILTERS BY CLEANING OR REPLACEMENT | $3,056 | $843 | Implemented |
MI0233 # 11 Y:2012 | 11 | 2012 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,084 | $80 | Implemented |
MI0233 # 10 Y:2012 | 10 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,631 | $2,050 | Implemented |
MI0233 # 09 Y:2012 | 09 | 2012 | INSTALL OCCUPANCY SENSORS | $5,193 | $800 | Implemented |
MI0233 # 08 Y:2012 | 08 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,430 | $2,665 | Implemented |
MI0233 # 07 Y:2012 | 07 | 2012 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $5,508 | $5,069 | Not Implemented |
MI0233 # 06 Y:2012 | 06 | 2012 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $7,406 | $1,060 | Not Implemented |
MI0233 # 05 Y:2012 | 05 | 2012 | OPTIMIZE PLANT POWER FACTOR | $10,216 | $11,120 | Not Implemented |
MI0233 # 04 Y:2012 | 04 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $12,400 | $1,660 | Implemented |
MI0233 # 03 Y:2012 | 03 | 2012 | INSTALL PARTITIONS TO REDUCE SIZE OF CONDITIONED SPACE | $44,157 | $11,632 | Not Implemented |
MI0233 # 01 Y:2012 | 01 | 2012 | CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD | $246,388 | $33,021 | Implemented |
AM0617 # 01 Y:2012 | 01 | 2012 | DEVELOP STANDARD OPERATING PROCEDURES | $191,786 | $6,200 | Not Implemented |
AM0617 # 09 Y:2012 | 09 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $630 | $300 | Implemented |
AM0617 # 08 Y:2012 | 08 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $911 | $5,377 | Implemented |
AM0617 # 07 Y:2012 | 07 | 2012 | RECYCLE WHITE WATER | $1,161 | $7,179 | Implemented |
AM0617 # 06 Y:2012 | 06 | 2012 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,871 | $64 | Implemented |
AM0617 # 05 Y:2012 | 05 | 2012 | INSTALL OCCUPANCY SENSORS | $2,056 | $1,562 | Implemented |
AM0617 # 04 Y:2012 | 04 | 2012 | MODIFY PROCESS TO REDUCE MATERIAL USE/COST | $2,146 | $0 | Implemented |
AM0617 # 03 Y:2012 | 03 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,264 | $2,775 | Implemented |
AM0617 # 02 Y:2012 | 02 | 2012 | RECOVER WASTE HEAT FROM EQUIPMENT | $153,000 | $375,000 | Not Implemented |