Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

20

matching recommendations
Reset
SIC 3861 Photographic Equipment And Supplies
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
UD0870 # 02 Y:2012 02 2012 UPGRADE CONTROLS ON COMPRESSORS $5,228 $10,000 Implemented
UD0870 # 11 Y:2012 11 2012 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS $2,788 $3,000 Implemented
UD0870 # 10 Y:2012 10 2012 INSULATE BARE EQUIPMENT $1,512 $0 Implemented
UD0870 # 09 Y:2012 09 2012 ISOLATE HOT OR COLD EQUIPMENT $1,602 $4,000 Not Implemented
UD0870 # 08 Y:2012 08 2012 RECOVER WASTE HEAT FROM EQUIPMENT $2,567 $4,000 Not Implemented
UD0870 # 07 Y:2012 07 2012 USE MINIMUM STEAM OPERATING PRESSURE $7,517 $0 Implemented
UD0870 # 06 Y:2012 06 2012 REPAIR OR REPLACE STEAM TRAPS $10,454 $1,800 Implemented
UD0870 # 05 Y:2012 05 2012 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $1,199 $1,500 Implemented
UD0870 # 04 Y:2012 04 2012 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $3,610 $1,500 Implemented
UD0870 # 03 Y:2012 03 2012 USE / PURCHASE OPTIMUM SIZED COMPRESSOR $4,564 $16,800 Not Implemented
UD0870 # 01 Y:2012 01 2012 USE PHOTOCELL CONTROLS $1,385 $1,660 Implemented
UD0644 # 01 Y:2002 01 2002 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK $462,150 $500 Not Implemented
UD0644 # 09 Y:2002 09 2002 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $475 $1,348 Implemented
UD0644 # 08 Y:2002 08 2002 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $478 $500 Not Implemented
UD0644 # 07 Y:2002 07 2002 AIR CONDITION ONLY SPACE NECESSARY $1,285 $0 Implemented
UD0644 # 06 Y:2002 06 2002 UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT $2,953 $131 Implemented
UD0644 # 05 Y:2002 05 2002 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $2,764 $2,775 Not Implemented
UD0644 # 04 Y:2002 04 2002 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $6,397 $13,222 Not Implemented
UD0644 # 03 Y:2002 03 2002 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE $12,612 $0 Not Implemented
UD0644 # 02 Y:2002 02 2002 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE $18,360 $0 Implemented