Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
23
matching recommendationsSIC | 39 | Miscellaneous Manufacturing Industries |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OK0930 # 03 Y:2015 | 03 | 2015 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $4,131 | $0 | Implemented |
IP0049 # 02 Y:2015 | 02 | 2015 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,197 | $8 | Implemented |
IP0049 # 11 Y:2015 | 11 | 2015 | REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES | $3,976 | $21,474 | Implemented |
IP0049 # 04 Y:2015 | 04 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,009 | $70 | Implemented |
IP0049 # 01 Y:2015 | 01 | 2015 | PAY BILLS ON TIME TO AVOID LATE FEES | $4,118 | $0 | Implemented |
SU0396 # 05 Y:2015 | 05 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,889 | $930 | Implemented |
SU0396 # 06 Y:2015 | 06 | 2015 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $17,027 | $20,360 | Implemented |
SU0396 # 08 Y:2015 | 08 | 2015 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $18,009 | $17,408 | Implemented |
SU0396 # 10 Y:2015 | 10 | 2015 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $419 | $0 | Implemented |
SU0396 # 02 Y:2015 | 02 | 2015 | USE DRYING OVEN (BATCH TYPE) ON ALTERNATE DAYS OR OTHER OPTIMUM SCHEDULE TO RUN EQUIPMENT WITH FULL LOADS | $738 | $0 | Implemented |
SU0396 # 01 Y:2015 | 01 | 2015 | PAY BILLS ON TIME TO AVOID LATE FEES | $813 | $0 | Implemented |
SU0396 # 04 Y:2015 | 04 | 2015 | CHECK FOR ACCURACY OF UTILITY / POWER METERS | $243 | $0 | Implemented |
WM0074 # 02 Y:2015 | 02 | 2015 | CONDENSE OPERATION INTO ONE BUILDING | $2,174 | $0 | Implemented |
WM0074 # 09 Y:2015 | 09 | 2015 | INSTALL OR UPGRADE INSULATION ON HVAC DISTRIBUTION SYSTEMS | $1,625 | $1,774 | Implemented |
WM0074 # 08 Y:2015 | 08 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $784 | $225 | Implemented |
BD0456 # 10 Y:2015 | 10 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $606 | $400 | Implemented |
BD0456 # 07 Y:2015 | 07 | 2015 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $685 | $1,500 | Implemented |
BD0456 # 09 Y:2015 | 09 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,006 | $548 | Implemented |
NC0535 # 01 Y:2015 | 01 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,964 | $9,077 | Implemented |
NC0535 # 03 Y:2015 | 03 | 2015 | INSTALL OCCUPANCY SENSORS | $667 | $2,297 | Implemented |
NC0535 # 08 Y:2015 | 08 | 2015 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,917 | $100 | Implemented |
NC0535 # 09 Y:2015 | 09 | 2015 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,975 | $1,750 | Implemented |
NC0535 # 10 Y:2015 | 10 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $598 | $100 | Implemented |