Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
112
matching recommendationsSIC | 393 | Musical Instruments |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MO0279 # 06 Y:2000 | 06 | 2000 | REDUCE / ELIMINATE USE OF DISPOSABLE PRODUCT | $396 | $960 | Implemented |
MO0279 # 07 Y:2000 | 07 | 2000 | AUTOMATE FINISHING PROCESS | $6,240 | $205 | Implemented |
MO0279 # 08 Y:2000 | 08 | 2000 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,160 | $486 | Implemented |
CO0396 # 01 Y:1997 | 01 | 1997 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $3,020 | $1,690 | Implemented |
CO0396 # 02 Y:1997 | 02 | 1997 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $691 | $1,050 | Implemented |
CO0396 # 03 Y:1997 | 03 | 1997 | INSTALL OCCUPANCY SENSORS | $270 | $1,000 | Implemented |
CO0396 # 04 Y:1997 | 04 | 1997 | UPGRADE OBSOLETE EQUIPMENT | $180 | $540 | Implemented |
CO0396 # 05 Y:1997 | 05 | 1997 | TURN OFF EQUIPMENT WHEN NOT IN USE | $100 | $0 | Implemented |
CO0396 # 06 Y:1997 | 06 | 1997 | INSTALL MAGAZINES FOR TEMPORARY STORAGE | $12,600 | $3,600 | Implemented |
HO0154 # 01 Y:1997 | 01 | 1997 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,944 | $21,668 | Implemented |
HO0154 # 02 Y:1997 | 02 | 1997 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $178 | $575 | Not Implemented |
HO0154 # 03 Y:1997 | 03 | 1997 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $6,425 | $3,182 | Not Implemented |
HO0154 # 04 Y:1997 | 04 | 1997 | RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE LABOR COSTS | $15,600 | $10,800 | Not Implemented |
HO0154 # 05 Y:1997 | 05 | 1997 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $117,000 | $525,000 | Not Implemented |
HO0154 # 06 Y:1997 | 06 | 1997 | USE EVAPORATION TO CONCENTRATE MATERIAL | $2,563 | $10,000 | Implemented |
MS0029 # 01 Y:1995 | 01 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,203 | $11,327 | Implemented |
MS0029 # 02 Y:1995 | 02 | 1995 | DIRECT WARMEST AIR TO COMBUSTION INTAKE | $10,983 | $30,000 | Not Implemented |
MS0029 # 03 Y:1995 | 03 | 1995 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $1,062 | $45 | Implemented |
MS0029 # 04 Y:1995 | 04 | 1995 | USE WASTE HEAT TO PRODUCE STEAM TO DRIVE A STEAM TURBINE-GENERATOR | $53,973 | $165,000 | Not Implemented |
MS0029 # 05 Y:1995 | 05 | 1995 | INSTALL TIMERS AND/OR THERMOSTATS | $1,432 | $262 | Implemented |
AR0051 # 01 Y:1995 | 01 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,333 | $1,744 | Implemented |
AR0051 # 02 Y:1995 | 02 | 1995 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,125 | $200 | Implemented |
AR0051 # 03 Y:1995 | 03 | 1995 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $281 | $620 | Implemented |
AR0051 # 04 Y:1995 | 04 | 1995 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $438 | $390 | Implemented |
AR0047 # 01 Y:1995 | 01 | 1995 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,568 | $4,260 | Implemented |