Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
20
matching recommendationsSIC | 3993 | Signs And Advertising Specialities |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UU0073 # 07 Y:2004 | 07 | 2004 | DEMOLISH OLD BUILDING TO REDUCE TAX AND INSURANCE BILLS | $130 | $0 | Not Implemented |
UU0073 # 06 Y:2004 | 06 | 2004 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $10,500 | $15,000 | Not Implemented |
UU0073 # 05 Y:2004 | 05 | 2004 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $2,700 | $2,500 | Not Implemented |
UU0073 # 04 Y:2004 | 04 | 2004 | REUSE / RECYCLE/ SELL PAPER PRODUCTS | $2,434 | $0 | Not Implemented |
UU0073 # 03 Y:2004 | 03 | 2004 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $990 | $6,000 | Not Implemented |
UU0073 # 02 Y:2004 | 02 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,080 | $860 | Not Implemented |
UU0073 # 01 Y:2004 | 01 | 2004 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $8,250 | $8,000 | Not Implemented |
BD0267 # 11 Y:2004 | 11 | 2004 | USE SYNTHETIC LUBRICANT | $124 | $30 | Implemented |
BD0267 # 13 Y:2004 | 13 | 2004 | AUTOMATE PAYROLL SYSTEM | $9,750 | $2,500 | Not Implemented |
BD0267 # 12 Y:2004 | 12 | 2004 | CONVERT TO ELECTROSTATIC POWDER COATING | $11,120 | $5,174 | Implemented |
BD0267 # 01 Y:2004 | 01 | 2004 | RE-SIZE CHARGING OPENINGS OR ADD MOVABLE COVER OR DOOR | $14,742 | $10,000 | Not Implemented |
BD0267 # 10 Y:2004 | 10 | 2004 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $173 | $292 | Implemented |
BD0267 # 09 Y:2004 | 09 | 2004 | USE PHOTOCELL CONTROLS | $229 | $250 | Not Implemented |
BD0267 # 08 Y:2004 | 08 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $234 | $210 | Implemented |
BD0267 # 07 Y:2004 | 07 | 2004 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $364 | $0 | Implemented |
BD0267 # 06 Y:2004 | 06 | 2004 | INSTALL OCCUPANCY SENSORS | $749 | $720 | Implemented |
BD0267 # 05 Y:2004 | 05 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $818 | $60 | Implemented |
BD0267 # 04 Y:2004 | 04 | 2004 | USE RADIANT HEATER FOR SPOT HEATING | $2,983 | $4,250 | Not Implemented |
BD0267 # 03 Y:2004 | 03 | 2004 | RE-SIZE CHARGING OPENINGS OR ADD MOVABLE COVER OR DOOR | $3,575 | $3,000 | Not Implemented |
BD0267 # 02 Y:2004 | 02 | 2004 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $4,548 | $320 | Not Implemented |