Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
556
matching recommendationsSIC | 494 | Water Supply |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AS0504 # 04 Y:2021 | 04 | 2021 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,467 | $4,029 | Implemented |
AS0504 # 05 Y:2021 | 05 | 2021 | INSTALL OCCUPANCY SENSORS | $2,778 | $3,974 | Implemented |
AS0504 # 06 Y:2021 | 06 | 2021 | INSTALL HEAT PIPES / RAISE COOLING SETPOINT | $1,029 | $245 | Implemented |
AS0503 # 01 Y:2021 | 01 | 2021 | USE SOLAR HEAT TO MAKE ELECTRICTY | $316,547 | $4,413,360 | Implemented |
AS0503 # 02 Y:2021 | 02 | 2021 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $82,856 | $1,837 | Not Implemented |
AS0503 # 03 Y:2021 | 03 | 2021 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $35,467 | $918 | Implemented |
AS0503 # 04 Y:2021 | 04 | 2021 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $27,634 | $115 | Implemented |
AS0503 # 05 Y:2021 | 05 | 2021 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $25,372 | $918 | Implemented |
AS0503 # 06 Y:2021 | 06 | 2021 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $9,834 | $5,555 | Implemented |
AS0503 # 07 Y:2021 | 07 | 2021 | INSTALL OCCUPANCY SENSORS | $9,147 | $2,290 | Implemented |
AS0503 # 08 Y:2021 | 08 | 2021 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,438 | $14,828 | Implemented |
AS0503 # 09 Y:2021 | 09 | 2021 | INSTALL HEAT PIPES / RAISE COOLING SETPOINT | $2,192 | $434 | Not Implemented |
OK1038 # 01 Y:2021 | 01 | 2021 | INSTALL OCCUPANCY SENSORS | $563 | $1,944 | Not Implemented |
OK1038 # 02 Y:2021 | 02 | 2021 | USE COUNTER CURRENT RINSING TO REDUCE WASTE WATER | $24,443 | $2,171 | Not Implemented |
OK1038 # 03 Y:2021 | 03 | 2021 | INSTALL TIMERS AND/OR THERMOSTATS | $991 | $0 | Not Implemented |
OR0737 # 01 Y:2021 | 01 | 2021 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $7,782 | $0 | Not Implemented |
OR0737 # 02 Y:2021 | 02 | 2021 | USE OPTIMUM SIZE AND CAPACITY EQUIPMENT | $7,614 | $0 | Not Implemented |
OR0737 # 03 Y:2021 | 03 | 2021 | USE OPTIMUM SIZE AND CAPACITY EQUIPMENT | $5,949 | $0 | Not Implemented |
OR0737 # 04 Y:2021 | 04 | 2021 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,884 | $0 | Implemented |
OR0737 # 05 Y:2021 | 05 | 2021 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $3,820 | $8,556 | Implemented |
CL2011 # 01 Y:2020 | 01 | 2020 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,964 | $3,933 | Implemented |
CL2011 # 02 Y:2020 | 02 | 2020 | INSTALL OCCUPANCY SENSORS | $1,997 | $295 | Implemented |
CL2011 # 03 Y:2020 | 03 | 2020 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $587 | $0 | Implemented |
CL2011 # 04 Y:2020 | 04 | 2020 | MODIFY FACILITY TO AVOID EXCESS MAINTENANCE COSTS | $7,830 | $4,500 | Implemented |
CL2011 # 05 Y:2020 | 05 | 2020 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $1,975 | $400 | Implemented |