Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
46
matching recommendationsSIC | 494 | Water Supply |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UK2103 # 01 Y:2021 | 01 | 2021 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $51,422 | $0 | n/a |
UK2103 # 02 Y:2021 | 02 | 2021 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $54 | $63 | n/a |
UK2103 # 03 Y:2021 | 03 | 2021 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,386 | $4,128 | n/a |
UK2103 # 04 Y:2021 | 04 | 2021 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $328 | $0 | n/a |
NC0664 # 03 Y:2021 | 03 | 2021 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $75 | $300 | n/a |
NC0664 # 04 Y:2021 | 04 | 2021 | INSTALL OCCUPANCY SENSORS | $87 | $300 | n/a |
NC0664 # 02 Y:2021 | 02 | 2021 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $16,598 | $1,000 | n/a |
NC0664 # 01 Y:2021 | 01 | 2021 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,718 | $4,219 | n/a |
LS2101 # 02 Y:2021 | 02 | 2021 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $37,040 | $68,125 | Not Implemented |
LS2101 # 01 Y:2021 | 01 | 2021 | USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY | $167 | $25 | Not Implemented |
LS2101 # 03 Y:2021 | 03 | 2021 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $4,907 | $26,500 | Not Implemented |
CL2107 # 04 Y:2021 | 04 | 2021 | USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY | $35,390 | $0 | n/a |
CL2107 # 03 Y:2021 | 03 | 2021 | MODIFY FACILITY TO AVOID EXCESS MAINTENANCE COSTS | $950 | $4,500 | n/a |
CL2107 # 02 Y:2021 | 02 | 2021 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,152 | $2,480 | n/a |
CL2107 # 01 Y:2021 | 01 | 2021 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,074 | $19,482 | n/a |
UA0238 # 03 Y:2021 | 03 | 2021 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $1,093 | $16,210 | Implemented |
UA0238 # 02 Y:2021 | 02 | 2021 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,488 | $5,859 | Implemented |
UA0238 # 01 Y:2021 | 01 | 2021 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $161,890 | $279,811 | Implemented |
AS0508 # 02 Y:2021 | 02 | 2021 | ELIMINATE/REDUCE AN OPERATION | $20,000 | $200 | Implemented |
AS0508 # 03 Y:2021 | 03 | 2021 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $1,773 | $1,500 | Implemented |
AS0508 # 04 Y:2021 | 04 | 2021 | INSTALL HEAT PIPES / RAISE COOLING SETPOINT | $427 | $114 | Implemented |
AS0508 # 05 Y:2021 | 05 | 2021 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $389 | $529 | Implemented |
AS0508 # 01 Y:2021 | 01 | 2021 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $79,572 | $28,606 | Not Implemented |
AS0504 # 06 Y:2021 | 06 | 2021 | INSTALL HEAT PIPES / RAISE COOLING SETPOINT | $1,029 | $245 | Implemented |
AS0504 # 05 Y:2021 | 05 | 2021 | INSTALL OCCUPANCY SENSORS | $2,778 | $3,974 | Implemented |