Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
27
matching recommendationsSIC | 4941 | Water Supply |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MA0763 # 07 Y:2016 | 07 | 2016 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $940 | $3,880 | Not Implemented |
MA0763 # 06 Y:2016 | 06 | 2016 | USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY | $1,753 | $1,000 | Implemented |
MA0763 # 05 Y:2016 | 05 | 2016 | PAY UTILITY BILLS ON TIME | $2,873 | $500 | Implemented |
MA0763 # 04 Y:2016 | 04 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,321 | $5,078 | Implemented |
MA0763 # 03 Y:2016 | 03 | 2016 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $4,665 | $4,950 | Not Implemented |
MA0763 # 02 Y:2016 | 02 | 2016 | USE EXISTING DAM TO GENERATE ELECTRICITY | $14,909 | $68,625 | Not Implemented |
MA0763 # 01 Y:2016 | 01 | 2016 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $18,953 | $37,590 | Implemented |
IA0561 # 02 Y:2016 | 02 | 2016 | INSTALL OCCUPANCY SENSORS | $1,633 | $944 | Implemented |
IA0561 # 01 Y:2016 | 01 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,131 | $19,250 | Implemented |
IA0561 # 03 Y:2016 | 03 | 2016 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,312 | $560 | Implemented |
IA0561 # 04 Y:2016 | 04 | 2016 | UTILIZE SENSORS CONTROLLING ROOF AND WALL OPENINGS | $533 | $195 | Implemented |
IA0561 # 05 Y:2016 | 05 | 2016 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $504 | $70 | Not Implemented |
IA0561 # 06 Y:2016 | 06 | 2016 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,225 | $5,350 | Implemented |
MA0758 # 04 Y:2016 | 04 | 2016 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $917 | $960 | Implemented |
MA0758 # 01 Y:2016 | 01 | 2016 | INSTALL / REPAIR INSULATION ON CONDENSATE LINES | $2,549 | $2,836 | Implemented |
MA0758 # 02 Y:2016 | 02 | 2016 | REPLACE HIGH RESISTANCE DUCTS, PIPES, AND FITTINGS | $2,464 | $500 | Implemented |
MA0758 # 06 Y:2016 | 06 | 2016 | PAY UTILITY BILLS ON TIME | $672 | $500 | Implemented |
MA0758 # 05 Y:2016 | 05 | 2016 | REDUCE VENTILATION AIR | $754 | $3,000 | Not Implemented |
MA0758 # 03 Y:2016 | 03 | 2016 | INSTALL OCCUPANCY SENSORS | $2,272 | $1,450 | Implemented |
NC0567 # 01 Y:2016 | 01 | 2016 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $2,225 | $500 | Implemented |
NC0567 # 02 Y:2016 | 02 | 2016 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $15,323 | $500 | Implemented |
NC0567 # 03 Y:2016 | 03 | 2016 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $21,630 | $500 | Implemented |
NC0567 # 04 Y:2016 | 04 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,573 | $24,432 | Implemented |
NC0567 # 05 Y:2016 | 05 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,671 | $4,410 | Implemented |
NC0567 # 06 Y:2016 | 06 | 2016 | INSTALL OCCUPANCY SENSORS | $410 | $868 | Not Implemented |