Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,246
matching recommendationsARC | 2 | ENERGY MANAGEMENT |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
KU0208 # 11 Y:1986 | 11 | 1986 | IMPROVE LUBRICATION PRACTICES | $411 | $500 | Implemented |
KU0209 # 05 Y:1986 | 05 | 1986 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $11,981 | $20,000 | Implemented |
KU0209 # 07 Y:1986 | 07 | 1986 | INSTALL TIMERS AND/OR THERMOSTATS | $3,611 | $945 | Implemented |
KU0209 # 08 Y:1986 | 08 | 1986 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,187 | $5,000 | Implemented |
KU0209 # 09 Y:1986 | 09 | 1986 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,209 | $3,372 | Implemented |
KU0209 # 12 Y:1986 | 12 | 1986 | SHUT OFF PILOTS IN STANDBY EQUIPMENT | $809 | $0 | Implemented |
KU0209 # 13 Y:1986 | 13 | 1986 | KEEP BOILER TUBES CLEAN | $796 | $1,600 | Implemented |
KU0209 # 14 Y:1986 | 14 | 1986 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $736 | $50 | Implemented |
KU0209 # 15 Y:1986 | 15 | 1986 | INSTALL TURBULATORS | $392 | $2,500 | Implemented |
KU0209 # 16 Y:1986 | 16 | 1986 | REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED | $353 | $50 | Implemented |
KU0209 # 17 Y:1986 | 17 | 1986 | USE COMPRESSOR AIR FILTERS | $161 | $50 | Implemented |
KU0209 # 18 Y:1986 | 18 | 1986 | MINIMIZE BOILER BLOWDOWN WITH BETTER FEEDWATER TREATMENT | $135 | $0 | Implemented |
LT0059 # 01 Y:1986 | 01 | 1986 | INSTALL SET-BACK TIMERS | $1,810 | $260 | Implemented |
LT0059 # 03 Y:1986 | 03 | 1986 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $657 | $85 | Implemented |
LT0059 # 04 Y:1986 | 04 | 1986 | PLANT TREES OR SHRUBS NEAR WINDOWS TO SHIELD FROM SUNLIGHT | $741 | $1,440 | Implemented |
AT0049 # 01 Y:1986 | 01 | 1986 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $3,135 | $1,957 | Implemented |
AT0049 # 02 Y:1986 | 02 | 1986 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,090 | $3,879 | Implemented |
AT0049 # 04 Y:1986 | 04 | 1986 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $2,100 | $500 | Implemented |
AT0050 # 01 Y:1986 | 01 | 1986 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $859 | $400 | Implemented |
CO0068 # 01 Y:1986 | 01 | 1986 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $17,856 | $700 | Implemented |
CO0068 # 05 Y:1986 | 05 | 1986 | INSTALL / REPAIR INSULATION ON STEAM LINES | $6,055 | $14,709 | Implemented |
CO0068 # 07 Y:1986 | 07 | 1986 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $7,985 | $300 | Implemented |
CO0068 # 10 Y:1986 | 10 | 1986 | INCREASE AMOUNT OF CONDENSATE RETURNED | $1,616 | $2,600 | Implemented |
CO0068 # 11 Y:1986 | 11 | 1986 | REPAIR AND ELIMINATE STEAM LEAKS | $2,009 | $600 | Implemented |
CO0068 # 12 Y:1986 | 12 | 1986 | REDUCE INFILTRATION TO REFRIGERATED AREAS; ISOLATE HOT EQUIPMENT FROM REFRIGERATED AREAS | $2,238 | $1,800 | Implemented |