IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

142,949

matching recommendations
Reset
ARC 2 ENERGY MANAGEMENT
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
IC0214 # 02 Y:2019 02 2019 REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL $54,479 $37,103 Not Implemented
IC0214 # 03 Y:2019 03 2019 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $18,278 $18,800 Implemented
IC0214 # 04 Y:2019 04 2019 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $19,255 $68,455 Implemented
IC0214 # 05 Y:2019 05 2019 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $32,132 $4,600 Implemented
WV0576 # 01 Y:2019 01 2019 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $274,752 $432,000 Not Implemented
WV0576 # 02 Y:2019 02 2019 REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES $141,742 $375,000 Not Implemented
WV0576 # 03 Y:2019 03 2019 UPGRADE CONTROLS ON COMPRESSORS $51,831 $25,750 Not Implemented
WV0576 # 04 Y:2019 04 2019 ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM $13,307 $1,000 Implemented
WV0576 # 06 Y:2019 06 2019 DEVELOP A REPAIR/REPLACE POLICY $10,175 $833 Implemented
WV0576 # 07 Y:2019 07 2019 INSTALL OCCUPANCY SENSORS $5,850 $2,860 Implemented
WV0576 # 08 Y:2019 08 2019 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $5,463 $0 Not Implemented
WV0576 # 09 Y:2019 09 2019 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $2,759 $2,875 Implemented
OR0718 # 01 Y:2019 01 2019 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $84,306 $71,155 Not Implemented
OR0718 # 02 Y:2019 02 2019 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME $47,893 $5,142 Not Implemented
OR0718 # 03 Y:2019 03 2019 VENTILATION SYSTEM TO SHUT OFF WHEN ROOM IS NOT IN USE $7,386 $27,337 Not Implemented
UA0209 # 01 Y:2019 01 2019 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $5,815 $10,528 Implemented
UA0209 # 02 Y:2019 02 2019 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $17,697 $3,007 Implemented
UA0209 # 03 Y:2019 03 2019 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $36,956 $100 Not Implemented
UA0209 # 04 Y:2019 04 2019 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $72,891 $2,850 Implemented
UA0209 # 05 Y:2019 05 2019 SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY $1,176 $1,200 Not Implemented
MA0801 # 01 Y:2019 01 2019 RECOVER WASTE HEAT FROM EQUIPMENT $416,385 $525,000 Not Implemented
MA0801 # 02 Y:2019 02 2019 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA $7,204 $200 Not Implemented
MA0801 # 03 Y:2019 03 2019 RECOVER WASTE HEAT FROM EQUIPMENT $6,653 $8,930 Not Implemented
MA0801 # 04 Y:2019 04 2019 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $3,364 $4,110 Not Implemented
MA0801 # 05 Y:2019 05 2019 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $3,249 $1,250 Not Implemented