Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
147,636
matching recommendationsARC | 2. | ENERGY MANAGEMENT |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
TN0411 # 03 Y:1990 | 03 | 1990 | RECOVER WASTE HEAT FROM EQUIPMENT | $681 | $1,850 | Implemented |
TN0411 # 04 Y:1990 | 04 | 1990 | REPAIR AND ELIMINATE STEAM LEAKS | $429 | $190 | Implemented |
TN0411 # 05 Y:1990 | 05 | 1990 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,377 | $354 | Implemented |
TN0411 # 06 Y:1990 | 06 | 1990 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $948 | $0 | Implemented |
TN0411 # 07 Y:1990 | 07 | 1990 | INSTALL / REPAIR INSULATION ON CONDENSATE LINES | $211 | $482 | Implemented |
TN0411 # 08 Y:1990 | 08 | 1990 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $626 | $210 | Implemented |
TN0411 # 09 Y:1990 | 09 | 1990 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $317 | $0 | Implemented |
TN0411 # 10 Y:1990 | 10 | 1990 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $246 | $635 | Not Implemented |
OR0089 # 01 Y:1990 | 01 | 1990 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,753 | $8,531 | Not Implemented |
OR0089 # 02 Y:1990 | 02 | 1990 | RE-SIZE CHARGING OPENINGS OR ADD MOVABLE COVER OR DOOR | $14,100 | $5,000 | Implemented |
OR0089 # 03 Y:1990 | 03 | 1990 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $96 | $181 | Not Implemented |
OR0090 # 01 Y:1990 | 01 | 1990 | REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED | $64,713 | $5,000 | Implemented |
OR0090 # 02 Y:1990 | 02 | 1990 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $412 | $509 | Implemented |
OR0090 # 03 Y:1990 | 03 | 1990 | INSULATE BARE EQUIPMENT | $1,562 | $3,277 | Not Implemented |
OR0090 # 04 Y:1990 | 04 | 1990 | MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE | $1,098 | $2,400 | Not Implemented |
OR0090 # 05 Y:1990 | 05 | 1990 | OPTIMIZE PLANT POWER FACTOR | $687 | $1,950 | Not Implemented |
OR0090 # 06 Y:1990 | 06 | 1990 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $6,669 | $22,569 | Not Implemented |
RU0094 # 01 Y:1990 | 01 | 1990 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,951 | $80 | Implemented |
RU0094 # 02 Y:1990 | 02 | 1990 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $295 | $0 | Not Implemented |
RU0094 # 04 Y:1990 | 04 | 1990 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,303 | $0 | Implemented |
RU0095 # 01 Y:1990 | 01 | 1990 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $3,594 | $2,500 | Implemented |
RU0095 # 02 Y:1990 | 02 | 1990 | INSTALL / REPAIR INSULATION ON STEAM LINES | $2,404 | $72 | Not Implemented |
RU0095 # 03 Y:1990 | 03 | 1990 | REPAIR AND ELIMINATE STEAM LEAKS | $4,881 | $0 | Implemented |
RU0095 # 04 Y:1990 | 04 | 1990 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $4,156 | $375 | Not Implemented |
RU0095 # 05 Y:1990 | 05 | 1990 | INSTALL / REPAIR INSULATION ON CONDENSATE LINES | $454 | $269 | Not Implemented |