Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
143,597
matching recommendationsARC | 2. | ENERGY MANAGEMENT |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OK1113 # 05 Y:2024 | 05 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $125 | $611 | n/a |
OK1112 # 01 Y:2024 | 01 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $51,785 | $105,814 | n/a |
OK1112 # 02 Y:2024 | 02 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $7,481 | $488 | n/a |
OK1112 # 03 Y:2024 | 03 | 2024 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $8,094 | $626 | n/a |
OK1112 # 04 Y:2024 | 04 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $15,199 | $0 | n/a |
OK1112 # 05 Y:2024 | 05 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $66,259 | $17,620 | n/a |
OK1112 # 06 Y:2024 | 06 | 2024 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $681 | $100 | n/a |
OK1112 # 07 Y:2024 | 07 | 2024 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $52,088 | $38,766 | n/a |
UA0285 # 01 Y:2024 | 01 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $117,423 | $1,498,840 | n/a |
UA0285 # 02 Y:2024 | 02 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $682 | $250 | n/a |
UA0285 # 03 Y:2024 | 03 | 2024 | INSTALL TIMERS AND/OR THERMOSTATS | $461 | $116 | n/a |
UA0285 # 04 Y:2024 | 04 | 2024 | INSTALL OCCUPANCY SENSORS | $159 | $301 | n/a |
UA0285 # 05 Y:2024 | 05 | 2024 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $757 | $411 | n/a |
UA0285 # 06 Y:2024 | 06 | 2024 | OPTIMIZE PLANT POWER FACTOR | $20,619 | $5,049 | n/a |
IP0193 # 01 Y:2024 | 01 | 2024 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $6,354 | $0 | n/a |
IP0193 # 02 Y:2024 | 02 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,007 | $104 | n/a |
IP0193 # 03 Y:2024 | 03 | 2024 | CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES | $1,590 | $0 | n/a |
IP0193 # 04 Y:2024 | 04 | 2024 | RECOVER WASTE HEAT FROM EQUIPMENT | $28,687 | $10,184 | n/a |
IP0193 # 05 Y:2024 | 05 | 2024 | USE IMMERSION HEATING IN TANKS, MELTING POTS, ETC | $2,202 | $1,165 | n/a |
IP0193 # 06 Y:2024 | 06 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $513 | $972 | n/a |
DL0239 # 01 Y:2024 | 01 | 2024 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $17,306 | $1,250 | n/a |
DL0239 # 02 Y:2024 | 02 | 2024 | USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY | $6,623 | $17,500 | n/a |
DL0239 # 03 Y:2024 | 03 | 2024 | MINIMIZE BOILER BLOWDOWN WITH BETTER FEEDWATER TREATMENT | $37,050 | $110,000 | n/a |
DL0239 # 04 Y:2024 | 04 | 2024 | INSTALL / REPAIR INSULATION ON CONDENSATE LINES | $61,029 | $10,000 | n/a |
DL0239 # 05 Y:2024 | 05 | 2024 | PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT | $9,543 | $2,247 | n/a |