Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,116
matching recommendationsARC | 2. | ENERGY MANAGEMENT |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
DL0257 # 05 Y:2025 | 05 | 2025 | INSTALL TIMERS AND/OR THERMOSTATS | $291 | $131 | n/a |
DL0257 # 01 Y:2025 | 01 | 2025 | USE SOLAR HEAT TO MAKE ELECTRICTY | $58,383 | $470,000 | n/a |
DL0257 # 03 Y:2025 | 03 | 2025 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $343 | $0 | n/a |
DL0257 # 04 Y:2025 | 04 | 2025 | USE OPTIMUM TEMPERATURE | $1,329 | $0 | n/a |
DL0257 # 02 Y:2025 | 02 | 2025 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $4,000 | $0 | n/a |
LE0599 # 12 Y:2025 | 12 | 2025 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,690 | $12,500 | n/a |
LE0599 # 01 Y:2025 | 01 | 2025 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $15,231 | $50 | n/a |
LE0599 # 02 Y:2025 | 02 | 2025 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,295 | $100 | n/a |
LE0599 # 11 Y:2025 | 11 | 2025 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $32,291 | $137,607 | n/a |
LE0599 # 07 Y:2025 | 07 | 2025 | BURN A LESS EXPENSIVE GRADE OF FUEL | $2,581 | $4,000 | n/a |
LE0599 # 09 Y:2025 | 09 | 2025 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $8,397 | $22,164 | n/a |
LE0599 # 10 Y:2025 | 10 | 2025 | USE SOLAR HEAT TO MAKE ELECTRICTY | $39,348 | $166,600 | n/a |
LE0599 # 08 Y:2025 | 08 | 2025 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $808 | $1,500 | n/a |
LE0599 # 05 Y:2025 | 05 | 2025 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,274 | $2,000 | n/a |
LE0599 # 04 Y:2025 | 04 | 2025 | UPGRADE OBSOLETE EQUIPMENT | $66,584 | $25,000 | n/a |
LE0599 # 03 Y:2025 | 03 | 2025 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $24,855 | $7,000 | n/a |
OK1137 # 02 Y:2025 | 02 | 2025 | INSTALL OCCUPANCY SENSORS | $520 | $1,286 | n/a |
OK1137 # 09 Y:2025 | 09 | 2025 | INSTALL OR UPGRADE INSULATION ON HVAC DISTRIBUTION SYSTEMS | $1,109 | $2,120 | n/a |
OK1137 # 06 Y:2025 | 06 | 2025 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $8,920 | $6,940 | n/a |
OK1137 # 08 Y:2025 | 08 | 2025 | CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES | $558 | $410 | n/a |
OK1137 # 01 Y:2025 | 01 | 2025 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $641 | $985 | n/a |
OK1137 # 07 Y:2025 | 07 | 2025 | COMBINE UTILITY METERS | $682 | $80 | n/a |
OK1137 # 03 Y:2025 | 03 | 2025 | USE SOLAR HEAT TO MAKE ELECTRICTY | $31,249 | $160,056 | n/a |
OK1137 # 05 Y:2025 | 05 | 2025 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,886 | $1,320 | n/a |
OK1137 # 04 Y:2025 | 04 | 2025 | OPTIMIZE PLANT POWER FACTOR | $3,482 | $12,000 | n/a |