Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,411
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AR0192 # 05 Y:2000 | 05 | 2000 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $19,496 | $24,000 | Implemented |
AR0192 # 06 Y:2000 | 06 | 2000 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $160,000 | $45,600 | Implemented |
AR0192 # 01 Y:2000 | 01 | 2000 | OPTIMIZE PLANT POWER FACTOR | $12,065 | $11,950 | Not Implemented |
AR0192 # 04 Y:2000 | 04 | 2000 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $492 | $1,426 | Implemented |
AR0192 # 02 Y:2000 | 02 | 2000 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,251 | $1,567 | Implemented |
AR0191 # 03 Y:2000 | 03 | 2000 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $582 | $0 | Not Implemented |
AR0191 # 01 Y:2000 | 01 | 2000 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,022 | $1,877 | Implemented |
AR0191 # 05 Y:2000 | 05 | 2000 | INSTALL EQUIPMENT TO MOVE PRODUCT | $74,880 | $80,000 | Not Implemented |
AR0191 # 04 Y:2000 | 04 | 2000 | USE MAGNETIC TECHNOLOGY TO TREAT WATER | $12,000 | $10,374 | Implemented |
AR0191 # 02 Y:2000 | 02 | 2000 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,105 | $1,590 | Not Implemented |
AR0191 # 06 Y:2000 | 06 | 2000 | ELIMINATE/REDUCE REDUNDANT INSPECTIONS | $95,071 | $13,210 | Implemented |
AR0190 # 02 Y:2000 | 02 | 2000 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $551 | $0 | Implemented |
AR0190 # 04 Y:2000 | 04 | 2000 | RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE HANDLING COSTS | $249,600 | $6,949 | Implemented |
AR0190 # 01 Y:2000 | 01 | 2000 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $235 | $75 | Implemented |
AR0190 # 03 Y:2000 | 03 | 2000 | OPTIMIZE PLANT POWER FACTOR | $1,150 | $1,950 | Not Implemented |
AR0189 # 01 Y:2000 | 01 | 2000 | USE SYNTHETIC LUBRICANT | $2,906 | $0 | Not Implemented |
AR0189 # 05 Y:2000 | 05 | 2000 | RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE LABOR COSTS | $2,249 | $110 | Not Implemented |
AR0189 # 02 Y:2000 | 02 | 2000 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,227 | $5,679 | Not Implemented |
AR0189 # 04 Y:2000 | 04 | 2000 | INSTALL EQUIPMENT TO MOVE PRODUCT | $269,892 | $15,800 | Not Implemented |
AR0189 # 03 Y:2000 | 03 | 2000 | SELL OIL TO RECYCLER | $1,436 | $1,500 | Not Implemented |
AR0188 # 05 Y:2000 | 05 | 2000 | INSTALL AN UNINTERUPTABLE POWER SUPPLY | $60,000 | $3,000 | Implemented |
AR0188 # 03 Y:2000 | 03 | 2000 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $734 | $2,130 | Implemented |
AR0188 # 06 Y:2000 | 06 | 2000 | RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE LABOR COSTS | $23,850 | $16,000 | Not Implemented |
AR0188 # 01 Y:2000 | 01 | 2000 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $369 | $0 | Implemented |
AR0188 # 02 Y:2000 | 02 | 2000 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $759 | $3,641 | Implemented |