Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
4,685
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
BD0386 # 13 Y:2011 | 13 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $221 | $285 | Implemented |
BD0386 # 14 Y:2011 | 14 | 2011 | USE EVAPORATION TO CONCENTRATE MATERIAL | $6,567 | $10,000 | Implemented |
BD0385 # 01 Y:2011 | 01 | 2011 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $118,574 | $45,000 | Implemented |
BD0385 # 02 Y:2011 | 02 | 2011 | REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES | $22,473 | $10,000 | Implemented |
BD0385 # 03 Y:2011 | 03 | 2011 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $15,367 | $15,000 | Implemented |
BD0385 # 04 Y:2011 | 04 | 2011 | USE RADIANT HEATER FOR SPOT HEATING | $13,838 | $10,500 | Not Implemented |
BD0385 # 05 Y:2011 | 05 | 2011 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $7,342 | $9,000 | Implemented |
BD0385 # 06 Y:2011 | 06 | 2011 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $4,623 | $50 | Not Implemented |
BD0385 # 07 Y:2011 | 07 | 2011 | INSTALL OCCUPANCY SENSORS | $4,412 | $1,800 | Implemented |
BD0385 # 08 Y:2011 | 08 | 2011 | USE PHOTOCELL CONTROLS | $2,458 | $3,750 | Implemented |
BD0385 # 09 Y:2011 | 09 | 2011 | INSTALL SKYLIGHTS | $1,481 | $2,500 | Implemented |
BD0385 # 10 Y:2011 | 10 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $767 | $3,445 | Implemented |
BD0385 # 11 Y:2011 | 11 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $522 | $349 | Not Implemented |
BD0384 # 01 Y:2011 | 01 | 2011 | USE RADIANT HEATER FOR SPOT HEATING | $50,720 | $73,600 | Implemented |
BD0384 # 02 Y:2011 | 02 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $32,663 | $45,984 | Implemented |
BD0384 # 03 Y:2011 | 03 | 2011 | REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES | $13,232 | $3,000 | Not Implemented |
BD0384 # 04 Y:2011 | 04 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $8,079 | $1,400 | Not Implemented |
BD0384 # 05 Y:2011 | 05 | 2011 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $2,049 | $5,100 | Implemented |
BD0384 # 06 Y:2011 | 06 | 2011 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,941 | $2,000 | Implemented |
BD0384 # 07 Y:2011 | 07 | 2011 | INSTALL OCCUPANCY SENSORS | $1,067 | $1,067 | Implemented |
BD0384 # 08 Y:2011 | 08 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $614 | $525 | Implemented |
BD0384 # 09 Y:2011 | 09 | 2011 | USE EVAPORATION TO CONCENTRATE MATERIAL | $949 | $705 | Not Implemented |
BD0384 # 10 Y:2011 | 10 | 2011 | MODIFY STARTUP/SHUTDOWN TIMES | $543 | $20 | Not Implemented |
BD0383 # 01 Y:2011 | 01 | 2011 | RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR | $22,085 | $7,000 | Not Implemented |
BD0383 # 02 Y:2011 | 02 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $21,355 | $7,633 | Not Implemented |