Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
287
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
BD0222 # 13 Y:2002 | 13 | 2002 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $70,000 | $40,000 | Implemented |
BD0222 # 12 Y:2002 | 12 | 2002 | REPAIR AND ELIMINATE STEAM LEAKS | $126 | $100 | Not Implemented |
BD0222 # 08 Y:2002 | 08 | 2002 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,901 | $2,000 | Not Implemented |
BD0222 # 04 Y:2002 | 04 | 2002 | RECOVER HEAT FROM EXHAUSTED STEAM, HOT AIR OR HOT WATER | $6,079 | $6,000 | Not Implemented |
BD0222 # 07 Y:2002 | 07 | 2002 | INSTALL OCCUPANCY SENSORS | $2,219 | $1,425 | Not Implemented |
BD0222 # 06 Y:2002 | 06 | 2002 | INSTALL TURBULATORS | $2,272 | $3,500 | Not Implemented |
BD0222 # 05 Y:2002 | 05 | 2002 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,027 | $1,000 | Not Implemented |
BD0222 # 10 Y:2002 | 10 | 2002 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $652 | $0 | Not Implemented |
BD0222 # 09 Y:2002 | 09 | 2002 | INSULATE BARE EQUIPMENT | $1,141 | $1,018 | Not Implemented |
BD0222 # 14 Y:2002 | 14 | 2002 | AUTOMATE PAYROLL SYSTEM | $24,960 | $17,300 | Implemented |
BD0222 # 01 Y:2002 | 01 | 2002 | SUBSTITUTE HOT PROCESS FLUIDS FOR STEAM | $185,274 | $20,000 | Not Implemented |
BD0222 # 02 Y:2002 | 02 | 2002 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $8,898 | $12,020 | Implemented |
BD0222 # 03 Y:2002 | 03 | 2002 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,835 | $2,232 | Not Implemented |
BD0222 # 11 Y:2002 | 11 | 2002 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $10 | $200 | Not Implemented |
BD0222 # 15 Y:2002 | 15 | 2002 | PAY BILLS ON TIME TO AVOID LATE FEES | $2,004 | $0 | Not Implemented |
BD0221 # 04 Y:2002 | 04 | 2002 | USE RADIANT HEATER FOR SPOT HEATING | $2,178 | $3,000 | Not Implemented |
BD0221 # 08 Y:2002 | 08 | 2002 | INSTALL OCCUPANCY SENSORS | $365 | $4,000 | Implemented |
BD0221 # 01 Y:2002 | 01 | 2002 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $25,075 | $56,000 | Not Implemented |
BD0221 # 10 Y:2002 | 10 | 2002 | AUTOMATE PAYROLL SYSTEM | $1,365 | $2,500 | Not Implemented |
BD0221 # 09 Y:2002 | 09 | 2002 | CLEAR AND RENT EXISTING SPACE | $5,076 | $1,000 | Not Implemented |
BD0221 # 05 Y:2002 | 05 | 2002 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,881 | $3,000 | Implemented |
BD0221 # 02 Y:2002 | 02 | 2002 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $16,340 | $1,500 | Implemented |
BD0221 # 03 Y:2002 | 03 | 2002 | RECOVER WASTE HEAT FROM EQUIPMENT | $4,744 | $1,500 | Implemented |
BD0221 # 07 Y:2002 | 07 | 2002 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $529 | $900 | Not Implemented |
BD0221 # 06 Y:2002 | 06 | 2002 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $555 | $0 | Implemented |