Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
997
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
BS0122 # 01 Y:2019 | 01 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $10,031 | $14,455 | Not Implemented |
BS0122 # 02 Y:2019 | 02 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $13,702 | $8,000 | Not Implemented |
BS0122 # 03 Y:2019 | 03 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,341 | $1,630 | Not Implemented |
BS0122 # 04 Y:2019 | 04 | 2019 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $882 | $15 | Not Implemented |
BS0122 # 05 Y:2019 | 05 | 2019 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $2,219 | $5,725 | Not Implemented |
BS0122 # 06 Y:2019 | 06 | 2019 | BURN A LESS EXPENSIVE GRADE OF FUEL | $105,689 | $93,600 | Not Implemented |
BS0122 # 07 Y:2019 | 07 | 2019 | BURN WASTE TO PRODUCE STEAM TO DRIVE A STEAM TURBINE GENERATOR SET AND USE STEAM EXHAUST FOR HEAT | $322,973 | $1,002,400 | Not Implemented |
BS0121 # 01 Y:2019 | 01 | 2019 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $109 | $125 | Not Implemented |
BS0121 # 02 Y:2019 | 02 | 2019 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $178 | $218 | Not Implemented |
BS0121 # 03 Y:2019 | 03 | 2019 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $904 | $880 | Not Implemented |
BS0121 # 04 Y:2019 | 04 | 2019 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,514 | $1,010 | Not Implemented |
BS0121 # 05 Y:2019 | 05 | 2019 | INSULATE BARE EQUIPMENT | $3,663 | $512 | Not Implemented |
BS0121 # 06 Y:2019 | 06 | 2019 | INSTALL OCCUPANCY SENSORS | $354 | $796 | Not Implemented |
BS0121 # 07 Y:2019 | 07 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,509 | $810 | Not Implemented |
BS0121 # 08 Y:2019 | 08 | 2019 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $257 | $56 | Not Implemented |
BS0120 # 01 Y:2019 | 01 | 2019 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $1,949 | $2,100 | Not Implemented |
BS0120 # 02 Y:2019 | 02 | 2019 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $2,165 | $4,875 | Not Implemented |
BS0120 # 03 Y:2019 | 03 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,195 | $210 | Not Implemented |
BS0120 # 04 Y:2019 | 04 | 2019 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $463 | $1,200 | Not Implemented |
BS0120 # 05 Y:2019 | 05 | 2019 | INSTALL TIMERS AND/OR THERMOSTATS | $1,832 | $411 | Not Implemented |
BS0120 # 06 Y:2019 | 06 | 2019 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $218 | $105 | Implemented |
BS0120 # 07 Y:2019 | 07 | 2019 | USE SOLAR HEAT TO MAKE ELECTRICTY | $8,608 | $129,500 | Not Implemented |
BS0119 # 01 Y:2019 | 01 | 2019 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $36 | $30 | Not Implemented |
BS0119 # 02 Y:2019 | 02 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $126 | $165 | Not Implemented |
BS0119 # 03 Y:2019 | 03 | 2019 | REDUCE COMBUSTION AIR FLOW TO OPTIMUM | $2,022 | $30 | Not Implemented |